    Kaoko Metals lists with $6.5m raise, targets high-grade Chalkos Copper-Silver Project

    Kaoko Metals lists with $6.5m raise, targets high-grade Chalkos Copper-Silver Project

    Shaanika takes over as Chamber CEO as Malango retires after 20 years

    Shaanika takes over as Chamber CEO as Malango retires after 20 years

    General Copper targets 80% stake in Otjozondjupa 48,500ha licence

    General Copper targets 80% stake in Otjozondjupa 48,500ha licence

    Andrada expands Lithium Ridge drilling after 21m at 1.24% Li₂O and near-surface hits

    Andrada expands Lithium Ridge drilling after 21m at 1.24% Li₂O and near-surface hits

    Mining exports hit N$64.7bn as Namibia shifts focus to energy, oil and gas — Nandi-Ndaitwah

    Namibia says 51% free-carry mine ownership not policy

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas hits 50m at 7.9% CuEq in highest-grade Otavi intercept yet

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

    Pancontinental opens PEL 87 virtual data room to bidders

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Chamber of Mines to engage Govt after Namibia shed 3 points in Fraser Institute mining survey

    Namibia can unlock 18 000 mining jobs and billions if policy bottlenecks are cleared – Malango

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Gold

Kokoseb targets 656 jobs, 710-bed village

by Editor
April 8, 2026
in Gold
0
Kokoseb mine life set at 11+ years producing 177,000 ounces first 5 years
512
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Kokoseb will operate as a large-scale, round-the-clock open-pit gold mine, built on continuous drilling, blasting, hauling and on-site processing, with gold doré bars produced on site and flown out every two weeks from a dedicated helipad located near the processing plant for final refining.

At full operation, the project is expected to employ approximately 656 people, comprising both staff and contractors across mining, processing and administrative functions.

Most of these jobs are expected to be filled by Namibians, with only a limited number of expatriate specialists required for technical and management roles.

The workforce will operate on a 24-hour, three-shift system to sustain continuous production, with the majority accommodated on site in a 710-bed village under fly-in/fly-out and drive-in/drive-out arrangements, while some employees from nearby towns such as Uis and Omaruru will be transported daily to the site.

Beyond direct employment, the project is also expected to generate additional economic activity through procurement, services and supply chains linked to the mine.

That operational model sits at the centre of what is shaping up to be one of Namibia’s most significant new gold developments.

The Kokoseb Gold Project, being advanced by WIA Gold Limited in partnership with Epangelo Mining Company through the Mandarin Investments joint venture, is located on mining licence 274 within EPL 4818 in the Erongo Region, about 15 kilometres from Okombahe and 30 kilometres from Uis.

The mine is designed as a 12-year conventional open-pit operation with a main pit and a satellite pit, supported by a 5.25 million tonnes per annum processing plant.

Over an estimated 12-year life of mine, Kokoseb is expected to extract about 58.9 million tonnes of ore and 369 million tonnes of waste, translating into a strip ratio of roughly 6.3 to 1. The operation is targeting total gold recovery of approximately 1.65 million ounces, placing it firmly in the category of Namibia’s emerging mid- to large-scale gold producers.

Mining will follow a standard but intensive cycle. Ore and waste will be drilled and blasted using ammonium nitrate fuel oil explosives, then loaded by excavators onto large haul trucks. High-grade ore will be fed directly into the processing plant, while lower-grade material will be stockpiled and treated later, allowing the operation to optimise recovery over the full life of mine.

At the processing plant, ore will pass through a SAG and ball mill crushing circuit before undergoing gravity recovery and carbon-in-leach processing. The plant will also incorporate Anglo American Research Laboratories elution technology and electrowinning to produce gold doré bars on site. This integrated processing route is designed to maximise recovery efficiency from a deposit averaging about 1.0 gram per tonne, with higher-grade zones reaching around 1.4 grams per tonne.

What strengthens the project’s fundamentals is the scale and growth of the resource. Since exploration began in late 2021, Kokoseb has expanded rapidly, reaching a mineral resource estimate of 2.93 million ounces of gold as of June 2025, including a high-grade component of over 2 million ounces. The deposit remains open along strike and at depth, suggesting that the current mine plan may not be the final limit of the resource.

Infrastructure is being built to support a self-contained mining operation in a relatively remote area. The project will include three waste rock dumps, a dry-stack tailings storage facility, processing plant, explosives storage, workshops, fuel facilities and a dedicated helipad integrated into the gold handling system, alongside an accommodation village capable of housing 710 workers.

Environmental controls are central to the project design. Tailings will undergo cyanide destruction before being filtered and stacked dry, reducing water usage and long-term contamination risks. Waste rock and topsoil will be handled separately to enable progressive rehabilitation during operations rather than waiting until closure. The mine layout itself has been adjusted to avoid sensitive ecological areas and minimise disturbance to key landscape features within the licence area.

The project’s footprint, however, intersects with existing infrastructure and community land. A section of the D3714 district road currently runs across the orebody and will need to be diverted to allow mining to proceed safely. The licence area also borders the Tsiseb and Ohungu conservancies within the Okombahe Reserve, placing the project within a landscape where mining, conservation and community interests will need to coexist.

Kokoseb remains at a regulatory stage. An application for mining licence 274 was submitted to the Ministry of Industries, Mines and Energy in October 2025 and is still under review. Once approved, construction is expected to take about two years before the mine moves into full production.

What emerges from the project design is a clear picture of how Kokoseb will function: a high-throughput, mechanically driven gold operation employing hundreds of people continuously, with infrastructure, logistics and environmental safeguards scaled to match its size. At the same time, its long-term success will depend not only on production performance, but also on how effectively it navigates regulatory approvals, land-use pressures, and community expectations in one of Namibia’s more sensitive regions.

Share205Tweet128
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Otjikoto delivers N$13 billion revenue as 2025 gold output nears 200,000 ounces

Otjikoto’s Q1 2026 revenue rises to N$2.9 billion despite sharp drop in gold output

May 7, 2026
Kameelburg drilling confirms rare earth, strontium and niobium system

Aldoro hits 0.76% niobium over 11m, 2.94% REE at 74m at Kameelburg

May 7, 2026
Kaoko Metals lists with $6.5m raise, targets high-grade Chalkos Copper-Silver Project

Kaoko Metals lists with $6.5m raise, targets high-grade Chalkos Copper-Silver Project

May 6, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In