    Reviving the Moosehead in PEL 87

    Pancontinental’s Namibia oil drilling plans hinge on finding a partner

    Connected Minerals starts Phase 2 drilling at Etango North-East’s Ondapanda prospect

    Connected Minerals puts two Namibian uranium projects on hold

    Kaoko Metals expands Namibia copper exploration to three drilling rigs

    Kaoko Metals expands Namibia copper exploration to three drilling rigs

    Six Namibian contractors involved in Etango’s US$353m uranium mine construction

    Six Namibian contractors involved in Etango’s US$353m uranium mine construction

    China secures 60% of Etango uranium production

    China secures 60% of Etango uranium production

    Botswana’s Motheo copper mine produces 13,341 tonnes in three months

    Botswana’s Motheo copper mine produces 13,341 tonnes in three months

    Otavi REE assets drive Cazaly’s recent trading level of A$0.032

    Cazaly identifies two copper drilling targets at Abenab North

    Deep Yellow spends N$85m on Tumas uranium project in three months

    Deep Yellow spends N$85m on Tumas uranium project in three months

    Deep Yellow says Tumas engineering now more than 60% complete

    Deep Yellow moves closer to Nedbank credit approvals for Tumas uranium mine

    Woodside Energy opts out of PEL 87 farm-in deal before stop date of May 18, 2025

    Pancontinental proposes drilling first well at Namibia’s PEL 87 within two years

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Six Namibian contractors involved in Etango’s US$353m uranium mine construction

by Editor
October 29, 2026
in Uranium
0
Six Namibian contractors involved in Etango’s US$353m uranium mine construction
492
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

Six Namibian construction companies are carrying out work on Bannerman Energy’s US$353 million Etango uranium project in the Erongo Region, where approximately 523 contractor personnel are involved in the mine’s development ahead of planned first production in 2028.

Bannerman’s latest quarterly activities report, covering the period ended 30 September 2026, identifies three principal construction contractors and three smaller Namibian-owned businesses undertaking work ranging from the mine’s processing infrastructure and permanent water supply pipeline to fencing, culverts and a gatehouse.

The companies are Tulela Mining & Construction, K Neumayer Civil Contractors, AN Construction, Dappa Trading Group CC, Dannie Construction CC and Nelugo Trading Enterprises CC.

Their participation comes as Etango prepares to move from early construction works into full-scale development following the joint venture’s final investment decision on 23 October.

The report shows that bulk earthworks were approximately 99% complete, while concrete construction across the primary crusher and associated processing infrastructure had reached 86% of the planned volume under the first two construction phases.

Tulela Mining & Construction is producing aggregate for the mine’s heap leach drainage system, with approximately half of the required material already produced by the end of September.

The company’s work involves blasting, crushing and screening aggregate before it is stockpiled for use in the drainage system.

K Neumayer Civil Contractors is undertaking concrete construction at the primary crusher and other dry processing plant infrastructure, including the stockpile tunnel, secondary and tertiary crushing facilities, screening structures, fine ore silo and associated conveyors.

Approximately 14,700 cubic metres of concrete had been poured across these construction packages by the end of September, with the works preparing the processing infrastructure for subsequent structural, mechanical and piping installations.

AN Construction is responsible for construction of the permanent water supply pipeline, which was approximately 90% complete.

The work includes underground pipe installations, pressure testing, pipe bridge fabrication and pipe pedestal installations. The pipeline forms part of the mine’s permanent water infrastructure under Bannerman’s supply agreement with NamWater.

Smaller Namibian-owned businesses are also participating through subcontracting arrangements.

Dappa Trading Group CC is constructing the mine’s gatehouse through K Neumayer Civil Contractors, while Dannie Construction CC is undertaking fencing works.

Nelugo Trading Enterprises CC is responsible for in-situ culvert construction through Namibbeton.

Bannerman said these subcontracting opportunities form part of its approach to increasing local participation in the development of Etango and allowing smaller Namibian businesses to contribute directly to project delivery.

The report does not disclose the individual contract values, the combined value of work allocated to the six companies or how many of the 523 contractor personnel are Namibian nationals.

Bannerman said construction activities were progressing within budget and schedule, with the fourth phase of bulk earthworks expected to be completed in December.

The dry processing plant’s design was approximately 98% complete, while detailed structural engineering of the wet plant had reached 33%. Engineering work was also continuing on the project’s electricity infrastructure and the proposed sulphuric acid storage and handling facility at Walvis Bay.

The Etango joint venture approved full-scale construction on the basis of the Etango-8 development plan, which provides for average annual uranium oxide production of approximately 3.5 million pounds.

Bannerman estimates that US$64 million of the project’s US$353 million pre-production capital expenditure had been incurred by the end of September. The joint venture held approximately US$295 million in cash, excluding funds in Namibian subsidiaries, to finance the remaining construction expenditure.

Bannerman managing director and chief executive Gavin Chamberlain said the company’s early works programme had been delivered within budget and schedule, providing the foundation for full-scale construction.

“With our early works program transitioning into full-scale build activities, it is timely to recognise our outstanding multi-year execution. Delivered on budget and schedule, the early works program is truly a credit to all that have worked on it,” Chamberlain said.

Etango is expected to begin producing uranium in 2028, with the current construction programme providing continued work for Namibian contractors as the mine moves towards commissioning.

Share197Tweet123
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Reviving the Moosehead in PEL 87

Pancontinental’s Namibia oil drilling plans hinge on finding a partner

October 29, 2026
Connected Minerals starts Phase 2 drilling at Etango North-East’s Ondapanda prospect

Connected Minerals puts two Namibian uranium projects on hold

October 29, 2026
Kaoko Metals expands Namibia copper exploration to three drilling rigs

Kaoko Metals expands Namibia copper exploration to three drilling rigs

October 29, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Subscribe now to receive all mining sector and related news!

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Extractor Magazine will use the information you provide on this form to be in touch with you and to provide updates and marketing.
Subscribe