    Botswana’s Motheo copper mine produces 13,341 tonnes in three months

    Botswana’s Motheo copper mine produces 13,341 tonnes in three months

    Otavi REE assets drive Cazaly’s recent trading level of A$0.032

    Cazaly identifies two copper drilling targets at Abenab North

    Deep Yellow spends N$85m on Tumas uranium project in three months

    Deep Yellow spends N$85m on Tumas uranium project in three months

    Deep Yellow says Tumas engineering now more than 60% complete

    Deep Yellow moves closer to Nedbank credit approvals for Tumas uranium mine

    Woodside Energy opts out of PEL 87 farm-in deal before stop date of May 18, 2025

    Pancontinental proposes drilling first well at Namibia’s PEL 87 within two years

    Forsys’ Norasa in the making

    Asarian secures environmental approval for Norasa uranium project until 2029

    TotalEnergies warns delays will raise Venus oil project costs

    TotalEnergies warns delays will raise Venus oil project costs

    EU €1b funding package hangs in the balance after Namibia refused to sign the Samoa Agreement

    Walvis Bay to handle first 145,000-pound Malawi uranium shipment

    Elevate considers developing Marenica, Koppies simultaneously

    Elevate seeks ratification of 4.7m shares issued to Xanthos in Marenica deal

    Namibia’s next multi-mineral growth province

    Chinalco’s US$15m Opuwo acquisition awaits Namibia, China approvals

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Copper

Botswana’s Motheo copper mine produces 13,341 tonnes in three months

by Editor
October 28, 2026
in Copper
0
Botswana’s Motheo copper mine produces 13,341 tonnes in three months
494
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

Sandfire Resources produced 13,341 tonnes of copper and 631,000 ounces of silver at its Motheo mine in Botswana during the three months ended 30 September 2026, compared with 12,050 tonnes of copper and 423,000 ounces of silver during the corresponding period last year.

The Australian mining company said in its quarterly report released on 27 October that copper-equivalent production reached 16,137 tonnes, compared with 13,927 tonnes a year earlier, as the higher-grade A4 open pit continued contributing to production.

The A4 deposit supplied approximately half of the ore processed at Motheo during the quarter, while the mine processed 1.41 million tonnes of ore, compared with 1.77 million tonnes in the preceding June quarter.

Sandfire maintained its production forecast of between 50,000 and 56,000 tonnes of copper and between 2.4 million and 2.6 million ounces of silver for the financial year ending June 2027.

The company said Motheo’s processing facilities operated at an annualised rate of 5.6 million tonnes during the quarter.

Copper production costs decline

Motheo’s underlying operating cost decreased to US$48 per tonne of ore processed, compared with US$54 in the preceding quarter, while its implied C1 copper production cost fell to US$0.65 per pound from US$0.70.

The September 2025 quarter recorded a higher implied C1 cost of US$1.47 per pound.

Sandfire attributed the lower costs partly to favourable treatment and refining charges and the capitalisation of waste removal expenditure associated with the fourth-stage development of the T3 open pit.

However, the company warned that elevated global fuel prices could increase operating expenses during the remainder of the financial year.

Motheo remains adequately supplied with diesel and other essential consumables, although Sandfire’s annual cost projections assume that diesel prices will return to earlier levels during the second half of the financial year.

Chief executive Brendan Harris said the company was closely monitoring energy markets because of the mine’s reliance on diesel-powered open-pit mining equipment.

“We are continuing to closely monitor energy markets given the potential for currently elevated prices to persist and supply chains to be further affected, recognising the greater reliance of Motheo on diesel to undertake its open pit mining operations,” Harris said.

US$20 million spent on Motheo

Sandfire invested US$20 million at Motheo during the September quarter, including approximately US$14 million on waste removal and US$3 million on sustaining and strategic projects.

Another US$3 million was associated with the acquisition of the Kgolo East and West exploration licences, situated northeast of Motheo and near the Khoemacau underground mining complex.

The company also completed 6.5 kilometres of resource conversion and infill drilling across the T3 and A4 deposits, involving 27 drillholes.

The next phase of drilling at T3 will concentrate on improving confidence in mineral resources and confirming copper grades in areas scheduled for future mining.

Across its wider Botswana exploration portfolio, Sandfire completed 11.7 kilometres of drilling during the quarter, testing three regional prospects and another three areas within the Motheo mining hub.

Exploration at A4 identified enriched copper mineralisation approximately 200 metres below the existing open pit, extending westwards over several hundred metres.

Sandfire said additional funding and drilling equipment would be allocated to establish whether the mineralisation continues between the identified zones and assess the potential for future underground mining.

21MW solar plant under construction

Construction of a 21-megawatt solar power facility at Motheo continued during the quarter, with supporting structures installed and solar panel installation under way.

The facility is expected to supply approximately 30% of the mine’s annual stationary electricity requirements once operational, reducing reliance on external electricity supplies and exposure to future tariff increases.

Commissioning is scheduled to begin during the third quarter of Sandfire’s 2027 financial year.

Across its operations in Botswana and Spain, Sandfire produced 38,900 tonnes of copper-equivalent metal during the September quarter, compared with 35,600 tonnes during the corresponding period last year.

The company generated unaudited revenue of US$480 million and underlying earnings before interest, tax, depreciation and amortisation of US$272 million.

Sandfire ended September with net cash of US$342 million, compared with US$353 million at the end of June, after paying US$117 million in dividends to shareholders.

The company maintained its full-year production, operating cost and capital expenditure guidance.

Share198Tweet124
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Botswana’s Motheo copper mine produces 13,341 tonnes in three months

Botswana’s Motheo copper mine produces 13,341 tonnes in three months

October 28, 2026
Otavi REE assets drive Cazaly’s recent trading level of A$0.032

Cazaly identifies two copper drilling targets at Abenab North

October 28, 2026
Golden Deeps four critical metals find

Golden Deeps reports 23.2% zinc, 9.2% copper at Graceland as deeper drilling continues

October 28, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Subscribe now to receive all mining sector and related news!

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Extractor Magazine will use the information you provide on this form to be in touch with you and to provide updates and marketing.
Subscribe