    Midas targets three copper resources within six months

    Midas targets three copper resources within six months

    Askari Metals to become Highland Metals in strategic rebrand

    Askari Metals to become Highland Metals in strategic rebrand

    Customs clearance delays Elevate’s uranium beneficiation pilot plant results release

    Customs clearance delays Elevate’s uranium beneficiation pilot plant results release

    Andrada confirms lithium grades of up to 3.46% at Lithium Ridge

    Andrada returns 14.72% Li₂O as Lithium Ridge expands to 9km

    Deep Yellow spends about N$725m on Tumas during 12 months to June 2026

    Deep Yellow spends about N$725m on Tumas during 12 months to June 2026

    Bannerman’s Etango spending reaches about N$800 million in the year to June 2026

    Bannerman’s Etango spending reaches about N$800 million in the year to June 2026

    Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

    Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

    Namibian companies take leading role in Etango construction

    Namibian companies take leading role in Etango construction

    Frontier targets maiden Engo uranium resource in third quarter

    Frontier targets maiden Engo uranium resource in third quarter

    Noronex targets new Namibia drilling campaign before year-end

    Noronex targets new Namibia drilling campaign before year-end

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Uncategorized

Road agency maps out N$155 billion highway upgrade programme

by Editor
July 8, 2026
in Uncategorized
0
Road agency maps out N$155 billion highway upgrade programme
516
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

The Roads Authority has outlined an ambitious programme to rehabilitate and upgrade some of Namibia’s busiest transport corridors at an estimated cost of more than N$155 billion if all the projects are eventually developed into dual carriageways.

The investment programme covers key national highways linking Windhoek with the central, northern and coastal regions and aims to improve road safety, accommodate growing traffic volumes and support economic development.

According to the Roads Authority, the proposed upgrades range from more affordable 2+1 carriageway designs to full dual carriageways, with several projects already in the planning and design stages.

The single largest project is the proposed 82-kilometre Windhoek-Rehoboth (T0105) dual carriageway, estimated to cost N$12.8 billion, for which the design has already been completed.

Another major undertaking is the 173-kilometre Okahandja-Otjiwarongo (T0107) corridor. While the authority estimates a 2+1 carriageway would cost N$3.2 billion, converting the route into a full dual carriageway would require approximately N$27.1 billion. Partial design work covering 18.5 kilometres has already been completed.

North of Otjiwarongo, the 118-kilometre Otjiwarongo-Otavi (T0108) section is expected to cost N$2.2 billion as a 2+1 carriageway or N$18.5 billion as a dual carriageway, with design work scheduled to begin in 2027.

The 61-kilometre Otavi-Tsumeb (T0109) corridor carries an estimated 1,732 vehicles per day, including 652 heavy vehicles, meaning trucks account for 38% of total traffic. The project is estimated at N$1.1 billion for a 2+1 carriageway or N$9.5 billion for a dual carriageway, with design expected to commence this year.

On the coast, the Roads Authority plans to upgrade the 48-kilometre Swakopmund-Arandis (T0202) road at an estimated N$879 million for a 2+1 carriageway or N$7.5 billion for a dual carriageway. The corridor carries around 3,915 vehicles daily, including 1,054 heavy vehicles, representing 27% of total traffic. Design work is expected to begin during 2026.

The adjoining 89-kilometre Arandis-Usakos section would require N$1.6 billion for a 2+1 carriageway or N$13.9 billion for a dual carriageway. Design work has already been completed.

The authority also plans improvements on the 132-kilometre Omaruru-Otjiwarongo (T0204) corridor, estimated at N$2.4 billion for a 2+1 carriageway and N$20.6 billion for a dual carriageway. The road currently carries approximately 986 vehicles per day, of which 362 are heavy, representing 37% of traffic.

In the north-east, the 89-kilometre Grootfontein-Mururani (T0802) road is estimated to cost N$2.3 billion as a 2+1 carriageway or N$20 billion as a dual carriageway. The corridor records about 665 vehicles daily, with 310 heavy vehicles, meaning trucks account for 47% of traffic.

The adjoining 131-kilometre Mururani-Rundu (T0803) section carries similar traffic volumes and is estimated to cost N$2.4 billion for a 2+1 carriageway or N$20.5 billion for a dual carriageway.

Collectively, the Roads Authority estimates that constructing all nine projects as 2+1 carriageways would require about N$28.9 billion. Upgrading the same corridors to full dual carriageways would increase the investment requirement to approximately N$150.4 billion, while the inclusion of the already costed Windhoek-Rehoboth dual carriageway brings the total programme to about N$163.2 billion.

The authority said the programme is intended to improve safety and efficiency on some of Namibia’s busiest freight and passenger corridors but acknowledged that implementation faces several obstacles, including limited funding, project prioritisation, road user behaviour, inadequate enforcement, manual weighbridge processes, limited human resources and insufficient pedestrian facilities.

To address these challenges, the Roads Authority plans to focus on project preparation and funding mobilisation, road safety audits, intersection upgrades, improved lighting on major urban roads, construction of pedestrian bridges, deployment of speed-over-distance enforcement technology, automation of weighbridges and greater use of digital law enforcement systems.

Share206Tweet129
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Report backs Ongwe’s Omatjete project with C$8.5m exploration plan

Report backs Ongwe’s Omatjete project with C$8.5m exploration plan

July 29, 2026
Cazaly preps for detailed airborne survey over largest undrilled rare earth anomaly

Cazaly preps for detailed airborne survey over largest undrilled rare earth anomaly

July 29, 2026
Midas targets three copper resources within six months

Midas targets three copper resources within six months

July 29, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In