    Midas plans more drill rigs at Otavi copper-silver-gold project

    Midas plans more drill rigs at Otavi copper-silver-gold project

    Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

    Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

    Navachab welcomes 28 apprentices

    Navachab welcomes 28 apprentices

    Snow Lake Energy targets end of 2025 for Engo Valley Uranium Project’s maiden mineral resource estimate

    Engo Valley uranium project maiden resource set for mid-third quarter 2026

    Trigon’s smart exit – walks away with about US$25m net gain and a debt-free future

    New Horizon revives dewatering strategy at Kombat Copper

    Koryx Copper to raise N$26.6m from selling 16 million shares

    Koryx reports 150m at 0.45% CuEq, targets 92,000t annual copper output at Haib

    Omitiomire – Namibia’s next copper mine

    Appian Capital Advisory acquires 95% stake in Omitiomire Copper Project

    Langer Heinrich Mine hits 3 million pounds output as final ramp-up phase begins

    Langer Heinrich increases production to 1.29 million pounds in last quarter

    ReconAfrica might need more money for Kavango West drilling

    ReconAfrica targets May start for Kavango West 1X production testing

    EU backs Namibia’s push for mineral value addition and green industrialisation

    EU backs Namibia’s push for mineral value addition and green industrialisation

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Tumas uranium project technically ready, investment decision still price-driven

by Editor
March 2, 2026
in Uranium
0
Tumas uranium project technically ready, investment decision still price-driven
545
SHARES
1.6k
VIEWS
Share on FacebookShare on Twitter

Deep Yellow Limited says its flagship Tumas Uranium Project in Namibia is technically ready for development, with resource and reserve work, engineering, and infrastructure groundwork largely complete.

Still, it will only take a Final Investment Decision (FID) when long-term uranium prices justify construction.

In its March 2026 corporate update, the company reported that Tumas now hosts a total uranium resource of 118.2 million pounds of U₃O₈ and ore reserves of 79.5 million pounds.

The project is designed for a multi-decade mine life, with staged production capacity targeted at approximately 3.6 million pounds of U₃O₈ per annum in its initial phase.

Deep Yellow said that detailed engineering work is more than 65 per cent complete and that key project contracts, including major process plant equipment, have been tendered or awarded.

Bulk earthworks and site preparation are in progress. To support operations, the company has executed a Transmission Power Supply Agreement with NamPower for a dedicated 22 km, 220 kV grid connection capable of up to 4 MVA.

It continues detailed planning for water supply and other infrastructure.

The financial and technical readiness is evident in the company’s balance sheet, which showed a cash position of A$187 million at 31 December 2025 and a market capitalisation in the A$2.5 billion range, giving Deep Yellow flexibility to continue advancing projects without immediate equity raising.

Deep Yellow’s modelling indicates that at a long-term uranium contract price of US$82.50 per pound U₃O₈, Tumas would generate a post-tax net present value (NPV₈) of about US$577 million and an internal rate of return (IRR) of around 19 per cent, with initial capital expenditure (capex) estimated at US$474 million and all-in sustaining costs near US$45 per pound of U₃O₈ extracted.

The company reiterated that the timing for FID remains price contingent.

Deep Yellow confirmed it will sanction construction only when long-term contracts and pricing support project economics, rather than relying on short-term spot price strength.

This reflects a disciplined approach that delayed 2025 FID considerations in favour of strengthening contract certainty and price stability.

Share218Tweet136
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Midas plans more drill rigs at Otavi copper-silver-gold project

Midas plans more drill rigs at Otavi copper-silver-gold project

May 20, 2026
Wia Gold offloads Côte d’Ivoire permits to focus on Kokoseb

Wia raises N$1.1b (A$92m) to fast-track Kokoseb Gold Project toward production

May 20, 2026
Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

May 19, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In