    Public review opens for Koppies West uranium project application

    Elevate grows Namibian uranium footprint to 116 million pounds

    Galp’s long game: From HRT’s early dry wells to Namibia’s new oil dawn

    Galp confirms three-well drilling and testing campaign for Mopane

    Deep Yellow says Tumas engineering now more than 60% complete

    Deep Yellow says Tumas engineering now more than 60% complete

    Rhino drills appraisal well to test Capricornus oil extension

    Rhino drills appraisal well to test Capricornus oil extension

    Prospect Resources ‘forgotten’ lithium project

    Prospect Resources seeks partners for Omaruru lithium project after exploration halt

    Deep Yellow drills 133 holes at Tinkas, confirms uranium mineralisation

    Deep Yellow drills 133 holes at Tinkas, confirms uranium mineralisation

    Skeleton Coast Uranium closes N$95m funding, completes Namibia licence deal

    Skeleton Coast Uranium appoints South African firm Practara to fast-track Namibia resource reports

    Nyambe first African to be appointed international energy negotiators president-elect

    SNC advised BP to acquire 60% operating interest in PELs 97, 99 and 100 in Walvis Basin

    Paladin books US$47.3m Langer Heinrich sales, leans on market deals to meet deliveries

    Paladin books US$47.3m Langer Heinrich sales, leans on market deals to meet deliveries

    Oregen Energy moves to lay stake in Block 2812Ab, Orange Basin

    Multi-project oil province forms as FID timelines align for 2026–2027

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Tumas uranium project technically ready, investment decision still price-driven

by Editor
March 2, 2026
in Uranium
0
Tumas uranium project technically ready, investment decision still price-driven
534
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Deep Yellow Limited says its flagship Tumas Uranium Project in Namibia is technically ready for development, with resource and reserve work, engineering, and infrastructure groundwork largely complete.

Still, it will only take a Final Investment Decision (FID) when long-term uranium prices justify construction.

In its March 2026 corporate update, the company reported that Tumas now hosts a total uranium resource of 118.2 million pounds of U₃O₈ and ore reserves of 79.5 million pounds.

The project is designed for a multi-decade mine life, with staged production capacity targeted at approximately 3.6 million pounds of U₃O₈ per annum in its initial phase.

Deep Yellow said that detailed engineering work is more than 65 per cent complete and that key project contracts, including major process plant equipment, have been tendered or awarded.

Bulk earthworks and site preparation are in progress. To support operations, the company has executed a Transmission Power Supply Agreement with NamPower for a dedicated 22 km, 220 kV grid connection capable of up to 4 MVA.

It continues detailed planning for water supply and other infrastructure.

The financial and technical readiness is evident in the company’s balance sheet, which showed a cash position of A$187 million at 31 December 2025 and a market capitalisation in the A$2.5 billion range, giving Deep Yellow flexibility to continue advancing projects without immediate equity raising.

Deep Yellow’s modelling indicates that at a long-term uranium contract price of US$82.50 per pound U₃O₈, Tumas would generate a post-tax net present value (NPV₈) of about US$577 million and an internal rate of return (IRR) of around 19 per cent, with initial capital expenditure (capex) estimated at US$474 million and all-in sustaining costs near US$45 per pound of U₃O₈ extracted.

The company reiterated that the timing for FID remains price contingent.

Deep Yellow confirmed it will sanction construction only when long-term contracts and pricing support project economics, rather than relying on short-term spot price strength.

This reflects a disciplined approach that delayed 2025 FID considerations in favour of strengthening contract certainty and price stability.

Share214Tweet134
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Public review opens for Koppies West uranium project application

Elevate grows Namibian uranium footprint to 116 million pounds

April 28, 2026
Galp’s long game: From HRT’s early dry wells to Namibia’s new oil dawn

Galp confirms three-well drilling and testing campaign for Mopane

April 28, 2026
Deep Yellow says Tumas engineering now more than 60% complete

Deep Yellow says Tumas engineering now more than 60% complete

April 28, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In