• Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
Saturday, May 9, 2026
  • Login
The Extractor Magazine
  • Home
  • News
    • All
    • Africa
    • Biofuels
    • Climate
    • Copper
    • Exploration
    • Lithium
    • Minerals
    • Mining
    • Namibia
    • Nickel
    • Oil & Gas
    • Precious Metals
    • RIGS & VESSELS
    • Silver
    • Uranium
    Okanjande graphite to be upgraded into Battery Anode Material in a N$3b facility in France

    Northern Graphite begins relocating plant for Okanjande restart late 2027

    Kaoko Metals lists with $6.5m raise, targets high-grade Chalkos Copper-Silver Project

    Kaoko Metals lists with $6.5m raise, targets high-grade Chalkos Copper-Silver Project

    Shaanika takes over as Chamber CEO as Malango retires after 20 years

    Shaanika takes over as Chamber CEO as Malango retires after 20 years

    General Copper targets 80% stake in Otjozondjupa 48,500ha licence

    General Copper targets 80% stake in Otjozondjupa 48,500ha licence

    Andrada expands Lithium Ridge drilling after 21m at 1.24% Li₂O and near-surface hits

    Andrada expands Lithium Ridge drilling after 21m at 1.24% Li₂O and near-surface hits

    Mining exports hit N$64.7bn as Namibia shifts focus to energy, oil and gas — Nandi-Ndaitwah

    Namibia says 51% free-carry mine ownership not policy

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas hits 50m at 7.9% CuEq in highest-grade Otavi intercept yet

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

    Pancontinental opens PEL 87 virtual data room to bidders

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Gold

Otjikoto delivers N$13 billion revenue as 2025 gold output nears 200,000 ounces

by Editor
February 19, 2026
in Gold
0
Otjikoto delivers N$13 billion revenue as 2025 gold output nears 200,000 ounces
517
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

The Otjikoto Gold Mine delivered one of its strongest production years on record in 2025, producing 199,139 ounces of gold and generating US$685 million approximately N$13.02 billion in revenue as prices surged and output landed near the top of guidance.

The mine, in which B2Gold Corp holds a 90% interest, converted production scale and metallurgical efficiency into strong cash generation during its final year of open-pit mining.

Average realised gold prices reached US$3,449 per ounce (about N$65,531/oz) for the year, rising sharply to US$4,175 per ounce (around N$79,325/oz) in the fourth quarter, amplifying the revenue impact of each ounce produced.

Production momentum was most visible in the final quarter, when Otjikoto produced 50,793 ounces, significantly above expectations.

The outperformance was driven by the continued processing of high-grade open-pit stockpiles after mining activities in the pit ended at the beginning of the quarter.

For the full year, the operation processed 3.44 million tonnes of ore at an average grade of 1.83 g/t and maintained an average gold recovery of 98.7%, underscoring the mine’s operational stability and processing efficiency.

Cash operating costs for 2025 averaged US$658 per ounce produced (approximately N$12,502/oz) and US$656 per ounce sold (around N$12,464/oz), below the midpoint of guidance.

All-in sustaining costs were held to US$969 per ounce sold (about N$18,411/oz), at the low end of the guided range. Lower-than-budgeted sustaining capital expenditure further strengthened cash flow during the year.

Capital expenditure at Otjikoto totalled US$24 million (roughly N$456 million) in 2025, focused mainly on underground development at Wolfshag, expansion of the tailings storage facility, early development work at the Antelope deposit and mobile equipment rebuilds.

Sustaining capital spending came in about US$8 million (approximately N$152 million) below budget, largely due to slower-than-planned underground development, reinforcing the mine’s cash contribution in a high-price environment.

With open-pit mining completed late in the year, attention has shifted to the underground growth pipeline. In September 2025, B2Gold approved the development of the Antelope underground deposit following optimisation work that reduced estimated pre-production capital costs from US$129 million (about N$2.45 billion) to approximately US$105 million (around N$1.99 billion).

The preliminary economic assessment outlines an initial five-year mine life producing roughly 327,000 ounces, with Antelope expected to lift Otjikoto’s annual production to around 110,000 ounces between 2029 and 2032 when combined with stockpile processing, subject to the uncertainties associated with inferred mineral resources.

Gold production at Otjikoto is expected to moderate in 2026 to between 70,000 and 90,000 ounces as the operation transitions fully to underground mining at Wolfshag, supplemented by existing low-grade stockpiles.

Capital expenditure is forecast to rise to about US$57 million (approximately N$1.08 billion) in 2026, reflecting increased underground development and progress on the Antelope project, as the mine reshapes itself from an open-pit operation into a longer-life underground producer within Namibia’s gold sector.

Share207Tweet129
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Okanjande graphite to be upgraded into Battery Anode Material in a N$3b facility in France

Northern Graphite begins relocating plant for Okanjande restart late 2027

May 7, 2026
Otjikoto delivers N$13 billion revenue as 2025 gold output nears 200,000 ounces

Otjikoto’s Q1 2026 revenue rises to N$2.9 billion despite sharp drop in gold output

May 7, 2026
Kameelburg drilling confirms rare earth, strontium and niobium system

Aldoro hits 0.76% niobium over 11m, 2.94% REE at 74m at Kameelburg

May 7, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In