    NDP6 – Five mines to power a nuclear future by 2030

    Bannerman reserves 40% of Etango uranium for buyers outside Chinese partnership

    Bannerman eyes US$367m expansion to double Etango uranium processing capacity

    Bannerman eyes US$367m expansion to double Etango uranium processing capacity

    Bannerman identifies three uranium exploration prospects around Etango

    Bannerman identifies three uranium exploration prospects around Etango

    Core Energy starts 2 650m uranium drilling at Barking Gecko in Namibia

    Core Energy starts 2 650m uranium drilling at Barking Gecko in Namibia

    Aldoro completes Avondschaduw drilling, moves rig to Kameelburg for three niobium holes

    Aldoro completes Avondschaduw drilling, moves rig to Kameelburg for three niobium holes

    Okopa pursues early copper production at Cornerstone Copper Project

    Okopa pursues early copper production at Cornerstone Copper Project

    QatarEnergy acquires 25% stake in Chevron’s PEL 82

    QatarEnergy grows offshore licence count to five

    Forsys’ Norasa in the making

    Asarian begins 4,500-metre uranium drilling programme at Namibplaas

    Cobre plans copper demonstration plant at Botswana’s Ngami Project in second half of 2027

    Cobre plans copper demonstration plant at Botswana’s Ngami Project in second half of 2027

    Leviathan intersects 0.47% copper at Central Project in Botswana

    Leviathan intersects 0.47% copper at Central Project in Botswana

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Magazine

B2Gold’s Antelope becomes the 2026–2027 capital centre

by Editor
January 12, 2026
in Magazine
0
All eyes on Antelope deposit as Otjikoto open pit mining operations end in 3Q 2025
550
SHARES
1.6k
VIEWS
Share on FacebookShare on Twitter

B2Gold’s clearest stated plan for Namibia in the near term is to execute the spend tied to the Antelope underground project at the Otjikoto Mine near Otavi.

In its Q3 2025 results disclosure, B2Gold said further optimisation work on a small-scale, low-cost underground mine concept at Antelope has reduced the estimated pre-production capital requirement from US$129 million to US$105 million, and that “the majority of pre-production capital is expected to be spent in 2026 and 2027.”

B2Gold also said it approved a development decision on Antelope on September 15, 2025, marking the point at which the project moved beyond study work into an execution pathway within the company’s planning.

Translating those capital figures into Namibian dollars gives a clearer sense of local scale.

Using the Bank of Namibia’s published NAD per US dollar of about N$16.46 to US$1 as shown on its rates page (latest update shown as January 11, 2026), the revised US$105 million estimate equates to roughly N$1.73 billion, while the earlier US$129 million estimate equates to roughly N$2.12 billion.

The optimisation B2Gold described, therefore, implies an indicative reduction of about US$24 million, or roughly N$395 million at that reference rate.

Although these conversions are directional and will move with the exchange rate, they accurately reflect the order of magnitude implied by B2Gold’s own US-dollar guidance.

B2Gold’s emphasis on Antelope spending in 2026–2027 sits within a broader operational transition at Otjikoto that the company has been flagging for some time.

According to B2Gold, “open pit mining operations are scheduled to conclude in the third quarter of 2025,” while underground mining operations at Wolfshag are “expected to continue into 2027.”

That timeline frames Antelope as the key lever in the mine plan once the open pit winds down and the operation becomes increasingly reliant on underground sources and stockpiles to keep the plant supplied.

B2Gold’s own disclosure explains why Antelope matters beyond being a capital line item.

In the Q3 2025 results release, the company summarised the Antelope preliminary economic assessment (PEA) as indicating an initial mine life of five years and total production of 327,000 ounces, averaging approximately 65,000 ounces per year.

B2Gold added that, “in combination with the processing of existing low-grade stockpiles,” production from Antelope has the potential to increase Otjikoto Mine production to approximately 110,000 ounces per year from 2029 through 2032.

This is the company’s stated case for Antelope: it is designed to support Otjikoto’s production profile later in the decade materially and to help bridge the operation into the period when stockpiles and underground sources become increasingly central.

In the Q3 2025 release, B2Gold says the majority of the Antelope pre-production is expected to be spread across 2026 and 2027.

With Wolfshag underground mining expected to continue into 2027, B2Gold is effectively signalling a narrowing window to secure the next ore source to underpin the processing operation.

B2Gold has also noted that exploration results indicate potential to extend underground production at Wolfshag beyond 2027.

However, the company still views Antelope as a distinct, planned contributor that could supplement processing operations and support output into the next decade.

The end of open-pit mining shifts operational emphasis toward underground development rates, scheduling discipline, ground conditions, ventilation and pumping requirements, and the ability to maintain steady plant feed.

A project like Antelope, once moved into execution, tends to pull forward spending on underground development, surface infrastructure, services, and equipment, along with the engineering and procurement activity needed to progress from a development decision into construction and production readiness.

B2Gold’s statement that most pre-production capital will be spent in 2026 and 2027 is therefore a clear signal that the company views those two years as the decisive build period for Antelope.

Antelope is not just an engineering milestone but a roughly N$1.7 billion pre-production capital programme at today’s exchange-rate range, and B2Gold is signalling that most of that capital intensity will land in the next two calendar years.

Share220Tweet138
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Namibia’s next multi-mineral growth province

Celsius Resources targets June deal for Opuwo Cobalt-Copper project sale

May 25, 2026
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
NDP6 – Five mines to power a nuclear future by 2030

Bannerman reserves 40% of Etango uranium for buyers outside Chinese partnership

November 12, 2026
Bannerman eyes US$367m expansion to double Etango uranium processing capacity

Bannerman eyes US$367m expansion to double Etango uranium processing capacity

November 12, 2026
Bannerman identifies three uranium exploration prospects around Etango

Bannerman identifies three uranium exploration prospects around Etango

November 12, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Subscribe now to receive all mining sector and related news!

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Extractor Magazine will use the information you provide on this form to be in touch with you and to provide updates and marketing.
Subscribe