• Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
Sunday, May 3, 2026
  • Login
The Extractor Magazine
  • Home
  • News
    • All
    • Africa
    • Biofuels
    • Climate
    • Copper
    • Exploration
    • Lithium
    • Minerals
    • Mining
    • Namibia
    • Nickel
    • Oil & Gas
    • Precious Metals
    • RIGS & VESSELS
    • Silver
    • Uranium
    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

    Pancontinental opens PEL 87 virtual data room to bidders

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Chamber of Mines to engage Govt after Namibia shed 3 points in Fraser Institute mining survey

    Namibia can unlock 18 000 mining jobs and billions if policy bottlenecks are cleared – Malango

    Uis Tin Mine: The world’s largest undeveloped open-cast hard rock tin deposit

    Andrada delays £7.7m loan repayment to fund Uis mine expansion

    Connected Minerals completes maiden RC drilling at Etango North-East, moves rig to Swakopmund Uranium Project

    Connected pauses work on its Namibian uranium assets as cash falls to A$2.8m

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas declares maiden 10.5Mt at 1.6% copper and 21g/t silver resource at Otavi projects

    Public review opens for Koppies West uranium project application

    Elevate grows Namibian uranium footprint to 116 million pounds

    Galp’s long game: From HRT’s early dry wells to Namibia’s new oil dawn

    Galp confirms three-well drilling and testing campaign for Mopane

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Rosatom’s Namibian affiliate Headspring’s 4-year wait for permit worries lawmakers

by Editor
July 12, 2025
in Uranium
0
When it comes to uranium, Namib Desert does not disappoint
549
SHARES
1.6k
VIEWS
Share on FacebookShare on Twitter

A four-year delay in securing permits has left Headspring Investments’ uranium exploration project in Namibia’s Omaheke region at a standstill, highlighting years of regulatory hurdles and frustration among lawmakers and company officials alike.
Headspring Investments (Pty) Ltd is wholly owned by Uranium One, which in turn is 100% owned by the Russian state atomic energy company Rosatom State Atomic Energy Corporation.
As Namibia’s local affiliate, Headspring explores and develops uranium deposits in the Omaheke region under Rosatom’s ISR expertise, including their flagship Wings Project.
Headspring’s permit application has been pending since 2021, when the government revoked its drilling permissions, halting all on-the-ground work.
The company says this suspension left its exploration programme incomplete and has kept the project in the pre-feasibility stage ever since.
Headspring has indicated that preparations for a pilot test programme are ready to proceed, but cannot move forward without final regulatory approvals.
This most recent delay is only the latest chapter in a long-running saga.
Headspring first began exploring for uranium in 2011 and launched drilling in 2012. But by 2013, operations were suspended when the government imposed a moratorium on uranium exploration, citing concerns about in-situ leaching techniques and the potential risk to groundwater.
At that time, the company had completed less than 60% of its planned drilling programme.
After several years of regulatory uncertainty, the company resumed limited fieldwork in 2016 and 2017, focusing on reconnaissance surveys, ground sampling, and mapping to refine exploration targets.
This groundwork paved the way for renewed drilling in 2018, following the lifting of the moratorium. By 2019, Headspring had reported the discovery of a promising sandstone-type uranium deposit.
However, even after the restart, the overall drilling programme remained incomplete.
The 2021 revocation of drilling permits once again halted all exploration, and the company has since been waiting nearly four years for approvals to resume.
While Headspring has not publicly disclosed the total financial impact of these delays, industry analysts note that such prolonged interruptions typically carry significant costs.
Direct expenses for partial drilling, site mobilisation, contractor fees, and logistical support could easily exceed several million US dollars.
Beyond that, the opportunity cost of missing favourable uranium market conditions, investor interest, and potential financing could result in further losses due to the extended delay.
If approvals are granted, restarting exploration will also require new compliance checks, environmental safeguards, community consultations, and remobilisation of drilling crews, adding further costs before any revenue can be realised.
Lawmakers have expressed frustration over the prolonged bureaucratic delays, questioning company representatives and regulatory authorities about the status of approvals.
They have warned that ongoing uncertainty risks deterring investment that could bring economic benefits and jobs to the Omaheke region.
Environmental concerns have long been at the centre of debate over the project.
Critics have cited fears that in situ leaching could contaminate groundwater.
However, in March of this year, then-chairperson of the joint parliamentary committee on economics, Tjekero Tweya, reported to parliament that investigations had found no evidence of such contamination during the initial drilling.
“There is no evidence to suggest that the mining method used has contaminated water,” Tweya told parliament. “Some 50% of exploration was carried out and nothing happened. Now, another 50% is needed for exploration. We are saying they should go ahead since there is no evidence.”
Tweya also noted that the original suspension was linked to operational issues, such as boreholes not being drilled according to permit requirements, some of which were left open, and extra drilling being conducted without permits—issues that Headspring has pledged to address if allowed to resume work.
During the latest committee meeting, lawmakers emphasised the need for clear timelines and accountability, stressing the importance of balancing environmental safeguards with the responsible development of Namibia’s mineral resources to benefit local communities and support the country’s role in supplying critical minerals to the global market.

Share220Tweet137
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

April 30, 2026
Northern Graphite plans restarting Okanjande in 2027

Okanjande moves closer to restart after Northern clears US$22m debt burden

April 30, 2026
Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

Pancontinental opens PEL 87 virtual data room to bidders

April 30, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In