    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

    Pancontinental opens PEL 87 virtual data room to bidders

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Chamber of Mines to engage Govt after Namibia shed 3 points in Fraser Institute mining survey

    Namibia can unlock 18 000 mining jobs and billions if policy bottlenecks are cleared – Malango

    Uis Tin Mine: The world’s largest undeveloped open-cast hard rock tin deposit

    Andrada delays £7.7m loan repayment to fund Uis mine expansion

    Connected Minerals completes maiden RC drilling at Etango North-East, moves rig to Swakopmund Uranium Project

    Connected pauses work on its Namibian uranium assets as cash falls to A$2.8m

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas declares maiden 10.5Mt at 1.6% copper and 21g/t silver resource at Otavi projects

    Public review opens for Koppies West uranium project application

    Elevate grows Namibian uranium footprint to 116 million pounds

    Galp’s long game: From HRT’s early dry wells to Namibia’s new oil dawn

    Galp confirms three-well drilling and testing campaign for Mopane

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News

Uranium mines in Erongo face a 500 cubic meter per hour water deficit

by Editor
May 9, 2025
in News
0
Uranium mines in Erongo face a 500 cubic meter per hour water deficit
523
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Uranium mining companies operating in the Erongo region face a 500 cubic meter per hour deficit.
The Erongo desalination plant (EDP) at Wlotzkasbaken, 35 km north of Swakopmund, supplies water to the mines and the towns in the region.
The plant owned by Orano can produce up to 20 million cubic metres (Mm3) of potable water annually.
Orano concluded an agreement with NamWater in August 2013 and has been producing up to 12 Mm3 per annum to augment the water supply to the other uranium mines and central coastal towns of Namibia, as there is a shortage of groundwater in the region.
According to the Chamber of Mines Namibia, the 500 cubic meter per hour deficit is primarily due to inadequate distribution infrastructure and increased water consumption by local municipalities.
The Chamber says it has been proactively addressing water supply challenges for the uranium sub-sector through the efforts of the Council Water Committee.
Key developments include commissioning a bypass connection and rehabilitation of a 34km pipeline from Omdel to the Orano desalination plant, boosting water supply by an additional 400-500 cubic meters per hour. The Chamber also says the commissioning of the 10th column at the Orano desalination plant in December 2024 will further increase capacity by 250 cubic meters per hour.
“Despite these advancements, a 500 cubic meter per hour deficit remains, primarily due to inadequate distribution infrastructure and increased water consumption by local municipalities,” the Chamber says.
To mitigate this, the Chamber is engaging NamWater on the urgency of installing three additional reservoirs of 20,000 cubic meters each, earlier than NamWater’s 2027 timeline.
The Chamber further says that the construction of a second desalination plant by Swakop Uranium and NamWater is expected to provide a sustainable solution in the long term.
“These advocacy initiatives underscore the Chamber’s commitment to resolving the immediate water supply challenges for the uranium sub-sector while addressing both immediate and future needs of mines in the Erongo region,” the Chamber says in its 2024 annual report.

Share209Tweet131
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

April 30, 2026
Northern Graphite plans restarting Okanjande in 2027

Okanjande moves closer to restart after Northern clears US$22m debt burden

April 30, 2026
Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

Pancontinental opens PEL 87 virtual data room to bidders

April 30, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In