    Midas targets three copper resources within six months

    Midas targets three copper resources within six months

    Askari Metals to become Highland Metals in strategic rebrand

    Askari Metals to become Highland Metals in strategic rebrand

    Customs clearance delays Elevate’s uranium beneficiation pilot plant results release

    Customs clearance delays Elevate’s uranium beneficiation pilot plant results release

    Andrada confirms lithium grades of up to 3.46% at Lithium Ridge

    Andrada returns 14.72% Li₂O as Lithium Ridge expands to 9km

    Deep Yellow spends about N$725m on Tumas during 12 months to June 2026

    Deep Yellow spends about N$725m on Tumas during 12 months to June 2026

    Bannerman’s Etango spending reaches about N$800 million in the year to June 2026

    Bannerman’s Etango spending reaches about N$800 million in the year to June 2026

    Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

    Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

    Namibian companies take leading role in Etango construction

    Namibian companies take leading role in Etango construction

    Frontier targets maiden Engo uranium resource in third quarter

    Frontier targets maiden Engo uranium resource in third quarter

    Noronex targets new Namibia drilling campaign before year-end

    Noronex targets new Namibia drilling campaign before year-end

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Gold

Wia Gold targets June 2025 for Kokoseb project scoping study completion

by Editor
April 28, 2025
in Gold
0
Wia Gold targets June 2025 for Kokoseb project scoping study completion
520
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Wia Gold is targeting June 2025 to complete the Kokoseb project scoping study to upgrade and increase the mineral resource estimate.
The Kokoseb Gold Project lies within the Okombahe exploration licence, which is held under a joint venture by Wia (80%) and the Namibian state-owed mining company Epangelo.
The Okombahe licence is part of Wia’s broader Damaran Belt tenure in Namibia, which consists of 12 tenements across a total area of over 2,700 km2.
Consultants from Namibia, South Africa and Australia are working across all major preliminary components of the study, which is targeted for completion in Quarter 3 of 2025.
Mine Geotech consultants visited the site and compiled geotechnical data for preliminary geotechnical analysis.
With re-logging, there is an opportunity to re-use approximately 1,000m of core from existing drilling in the initial geotechnical assessment.
The data from drilling since January 2025, along with proposed drilling in the current program, will provide sufficient data for use in planning the phase 1 geotechnical drilling program design.
The mining consultant’s scope of work was awarded and executed, including the commencement of open pit designs, waste dump locations, and other preliminary works.
The site satellite survey was finalised, and the digital terrain model, which incorporated a site survey of several ground control points, was delivered.
A high-level layout of surface infrastructure has been prepared.
The consultants for plant and non-processing infrastructure and comminution scope of work awarded and executed.
Wia Gold appointed consultants for the comminution design, process and non-process infrastructure aspects of the scoping study, including plant footprint for use in the layout of surface infrastructure.
The company awarded the hydrology and associated geophysics scope of work contract and received a desktop scoping report on water availability assessment. An application for water supply from NamWater, the state-owned water utility, was submitted to formalise the process.
Data is being gathered to support the assumptions required to develop tailings storage options (filtered and conventional slurry tailings) for the multi-criteria analysis of possibilities.
Limited tailings testing is being scoped to help inform the Scoping Study and subsequent phases.

Share208Tweet130
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Report backs Ongwe’s Omatjete project with C$8.5m exploration plan

Report backs Ongwe’s Omatjete project with C$8.5m exploration plan

July 29, 2026
Cazaly preps for detailed airborne survey over largest undrilled rare earth anomaly

Cazaly preps for detailed airborne survey over largest undrilled rare earth anomaly

July 29, 2026
Midas targets three copper resources within six months

Midas targets three copper resources within six months

July 29, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In