    Midas plans more drill rigs at Otavi copper-silver-gold project

    Midas plans more drill rigs at Otavi copper-silver-gold project

    Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

    Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

    Navachab welcomes 28 apprentices

    Navachab welcomes 28 apprentices

    Snow Lake Energy targets end of 2025 for Engo Valley Uranium Project’s maiden mineral resource estimate

    Engo Valley uranium project maiden resource set for mid-third quarter 2026

    Trigon’s smart exit – walks away with about US$25m net gain and a debt-free future

    New Horizon revives dewatering strategy at Kombat Copper

    Koryx Copper to raise N$26.6m from selling 16 million shares

    Koryx reports 150m at 0.45% CuEq, targets 92,000t annual copper output at Haib

    Omitiomire – Namibia’s next copper mine

    Appian Capital Advisory acquires 95% stake in Omitiomire Copper Project

    Langer Heinrich Mine hits 3 million pounds output as final ramp-up phase begins

    Langer Heinrich increases production to 1.29 million pounds in last quarter

    ReconAfrica might need more money for Kavango West drilling

    ReconAfrica targets May start for Kavango West 1X production testing

    EU backs Namibia’s push for mineral value addition and green industrialisation

    EU backs Namibia’s push for mineral value addition and green industrialisation

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Bannerman Energy spent N$33.5m on Etango project for quarter ending March 31

by Editor
April 26, 2024
in Uranium
0
526
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Bannerman Energy spent N$33.5 million (A$2.7 million) on exploring and developing the Etango Uranium Project in Namibia in the quarter that ended March 31, 2024.

The company says all Etango-8 cost estimates, including pre-production capex of about N$6.1 billion (US$320 million), remained materially unchanged for the Etango expansion and extension scoping study. 

Bannerman’s cash balance was N$393 million (A$31.7 million) as of March 31, 2024, compared to N$437 million (A$35.2 million) as of December 31, 2023.

During the quarter ended March 31, 2024, Bannerman completed the Etango expansion (XP) and extension scoping study, which evaluated two future phase options to each produce 95.2 Mlbs U3O8 over the life of mine.

The Etango-XP seeks to expand throughput capacity to 16 Mtpa after construction and ramp-up of the base case, increasing average annual production from 3.5 Mlbs to 6.7 Mlbs U3O8 post-expansion. 

The Etango extension wants to increase the mine’s operating life from 15 to 27 years without expanding throughput capacity. 

Bannerman Resources says the key Etango Project workstreams ‒ Front End Engineering and Design (FEED) – are highly advanced and on target to complete during the second quarter of 2024.

The dry plant process simulation was finalised, and vendor information was included for the leading mechanical equipment. 

The dry plant’s mass and water balance, piping, and instrument diagrams have been completed, and good progress has been made on the wet plant section.

Mechanical packages have all been received back from the market, and adjudications of the structural, mechanical, and piping packages have been completed. 

Packages for bulk earthworks and concrete have been adjudicated, and the final recommendation has been made for award. The rips dump design optimisation is on track to incorporate the selected vendor conveyor solution. 

A surface water management study was commissioned to review the current design and ensure the effectiveness of any potential flood mitigation measures.

 The early works contracts for the construction water supply and the mine access road are on schedule to achieve the planned completion date of July 2024.

Bannerman executive chairman Brandon Munro said the strong progression in project workstreams during the quarter steadily advanced the fully permitted Etango project towards construction, in parallel with financing and offtake marketing workstreams, as we drive towards being in a position to take a positive Final Investment Decision. 

“We were particularly pleased to demonstrate, via the Etango-XP/XT Scoping Study, the long-term optionality afforded by our large-scale Etango resource and a clear pathway towards becoming a 6.7 Mlbs pa producer,” Munro said.

Share210Tweet132
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Midas plans more drill rigs at Otavi copper-silver-gold project

Midas plans more drill rigs at Otavi copper-silver-gold project

May 20, 2026
Wia Gold offloads Côte d’Ivoire permits to focus on Kokoseb

Wia raises N$1.1b (A$92m) to fast-track Kokoseb Gold Project toward production

May 20, 2026
Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

Kaoko Metals begins preparations for maiden drilling at Chalkos and Karibib projects

May 19, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In