    Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

    Pancontinental opens PEL 87 virtual data room to bidders

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Chamber of Mines to engage Govt after Namibia shed 3 points in Fraser Institute mining survey

    Namibia can unlock 18 000 mining jobs and billions if policy bottlenecks are cleared – Malango

    Uis Tin Mine: The world’s largest undeveloped open-cast hard rock tin deposit

    Andrada delays £7.7m loan repayment to fund Uis mine expansion

    Connected Minerals completes maiden RC drilling at Etango North-East, moves rig to Swakopmund Uranium Project

    Connected pauses work on its Namibian uranium assets as cash falls to A$2.8m

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas declares maiden 10.5Mt at 1.6% copper and 21g/t silver resource at Otavi projects

    Public review opens for Koppies West uranium project application

    Elevate grows Namibian uranium footprint to 116 million pounds

    Galp’s long game: From HRT’s early dry wells to Namibia’s new oil dawn

    Galp confirms three-well drilling and testing campaign for Mopane

    Deep Yellow says Tumas engineering now more than 60% complete

    Deep Yellow says Tumas engineering now more than 60% complete

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News

Omico Mining says Omitiomire Copper Project bankable feasibility study expected in second half of 2024

by Editor
March 25, 2024
in News
0
Omico Mining says Omitiomire Copper Project bankable feasibility study expected in second half of 2024

~ai-3c19a76c-3079-45f9-89ee-96524d63c3ee_

562
SHARES
1.6k
VIEWS
Share on FacebookShare on Twitter

Omico Mining Corp says it will complete the bankable feasibility study for the Omitiomire Copper Project in the second half of 2024.
The bankable feasibility study was supposed to have been completed in the first quarter of 2024.
The Omitiomire Copper Project is in the Hockfeld area, Otjozodjupa region, northeast of Windhoek.
Omico Copper is a joint venture between and International Base Metals Limited.
UK-based private equity fund Greenstone Resources is the manager of Omico, which holds 95% of the Craton Project, with the Craton Foundation Trust holding the remaining 5%.
Craton Mining and Exploration, a subsidiary of the Australian company International Base Metals Limited, holds the Omitiomire mining licence 197.
The two parties agreed in 2019 that Greenstone would earn 51% of Craton in return for completing a bankable feasibility study (BFS) with a minimum expenditure of US$5 million.
After the bankable feasibility study, and assuming it meets the required future investment hurdles, IBML would have the option to either sell its remaining equity in Craton to Greenstone for US$7.5 million plus a 1.5% NSR royalty or invest in the future project to the extent of its equity holding.
Omico says the bankable feasibility study could not be completed as planned after Phase 3 metallurgical test work, indicating significantly lower acid consumption, faster leach cycle time, and higher recovery than expected.
As a result of these findings, Omico commissioned a final Phase 4 metallurgical test work programme starting in December 2023, which aimed at bringing this new approach to a bankable standard.
Omico says the expected bankable feasibility study outcomes, with a revised processing approach, include post-tax NPV8 of US$175 million, 18% IRR, with a capital intensity of US$14,100/t copper including mining fleet, C1 costs of US$4,700/t Cu and AISC of US$5,520/t Cu.
The assumption is that Omitiomire will produce 25-30ktpa Cu cathode within 13 or 14 years, with preproduction capital at US $360 million.
The plant capacity will be 6.7 Mtpa, while metallurgical recoveries were set at 80%, with acid consumption of 15 kg/tonne and leach cycle time of 200 days.

 

 

Share225Tweet141
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

Pancontinental opens PEL 87 virtual data room to bidders

April 30, 2026
Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

April 29, 2026
Chamber of Mines to engage Govt after Namibia shed 3 points in Fraser Institute mining survey

Namibia can unlock 18 000 mining jobs and billions if policy bottlenecks are cleared – Malango

April 29, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In