    Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

    Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

    Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

    Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

    Teach farmers to co-exist with mining – parliamentary committee on Omaheke exploration

    IAEA calls for more groundwater tests at Uranium One’s Wings project

    Skeleton Coast Uranium raises C$2.3 million for Namibia exploration

    Skeleton Coast Uranium raises C$2.3 million for Namibia exploration

    Paladin’s Namibia after-tax profit rises from US$1.8m to US$8.1m in September quarter

    Paladin’s Namibia after-tax profit rises from US$1.8m to US$8.1m in September quarter

    Langer Heinrich uranium revenue jumps 71% to US$304m

    Paladin banks on J Pit to meet 5.1 million to 5.6 million pound uranium target at Langer Heinrich

    Nandi-Ndaitwah says bureaucracy nearly cost Namibia US$2.5 billion Dangote investment

    Nandi-Ndaitwah says bureaucracy nearly cost Namibia US$2.5 billion Dangote investment

    Dangote wants more investment opportunities in Namibia after US$2.5 billion commitment

    Dangote wants more investment opportunities in Namibia after US$2.5 billion commitment

    Swakop Uranium plans three-pit uranium mine on 130 km² in Erongo

    Swakop Uranium plans three-pit uranium mine on 130 km² in Erongo

    Core Energy brings in Torque Drilling for Barking Gecko campaign

    Core Energy brings in Torque Drilling for Barking Gecko campaign

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Gold

Osino Resources eyes Kransberg aquifer for Twin Hills water supply

by Editor
July 9, 2025
in Gold, Magazine
0
Metso to deliver N$416m-equipment to Twin Hills Gold Project
548
SHARES
1.6k
VIEWS
Share on FacebookShare on Twitter

As Namibia’s arid heartland braces for another cycle of boom in gold mining, one question sits at the centre of environmental debate: where will all the water come from?

For Osino Resources, which is advancing the Twin Hills Gold Project near Karibib and Usakos, that question isn’t academic. It is existential. The company’s Environmental and Social Impact Assessment (ESIA) outlines a vision that must balance mining’s voracious water needs with the rights of local communities, the protection of fragile groundwater resources, and the ever-present risk of climate variability.

Twin Hills is no small venture. Osino’s feasibility studies estimate that it will require approximately 3,300 cubic metres of water per day, or around 1.1 million cubic metres annually, for processing, dust suppression, and support infrastructure once it is fully operational. In a country where average annual rainfall is among the lowest in sub-Saharan Africa, finding—and justifying—that volume is a significant challenge.

Tapping the Kranzberg Aquifer

The company’s ESIA, whose scoping report and Environmental Management Plan (EMP) were submitted for public review between 17 March and 14 April 2025, sets out its primary plan: tapping groundwater from on-site borefields and the larger Kranzberg Aquifer. Located near Usakos, the Kranzberg formation is a known regional aquifer that also serves farmers, towns, and other users in the Erongo region. Osino’s hydrogeological studies, which included extensive pump testing, suggest that the aquifer can sustainably yield approximately 460,800 cubic metres per year for the mine without threatening other users. However, this is based on cautious recharge estimates and conservative pumping plans.

To get this water to Twin Hills, Osino proposes a new pipeline from the Kranzberg borefields via Karibib to the mine site. The ESIA process for this water abstraction and transport system included public consultations, specialist hydrological modelling, and the development of a detailed Environmental Management Plan (EMP). This plan outlines obligations for continuous groundwater monitoring, adaptive management in the event of drawdowns exceeding thresholds, and clear mitigation steps in the event of aquifer stress.

Community concerns and consultation

Community feedback collected during the ESIA’s scoping phase focused sharply on this issue. Farmers, civic groups, and local authorities all flagged groundwater as a critical lifeline in an already water-stressed region. Osino’s consultants responded by building conservative pumping models and committing to share monitoring data transparently. The EMP includes triggers for modifying abstraction rates should monitoring reveal unintended impacts.

However, the company isn’t relying solely on a single aquifer. Recognising both the technical and social risks of relying entirely on the Kranzberg system, Osino’s ESIA outlines multiple contingency and diversification strategies designed to spread the burden and boost resilience.

Diversifying water sources

First among these is recycled process water. Twin Hills’ processing plant is being designed with a tailings filtration system to maximise water recovery, aiming for over 80% recycling of process water. The filtered tailings will be dry-stacked—a technology that uses far less water than conventional slurry tailings storage and reduces contamination risk.

Second, Osino is investigating the potential for treated municipal wastewater reuse, particularly from the Karibib sewage works. Upgrading this facility could provide a consistent supply of treated water for the mine while helping the town improve its sanitation infrastructure—a classic “win-win” scenario if managed effectively.

Third, the company is assessing options for managed aquifer recharge and surface water or sand storage systems, such as temporary dams in the Khan River. These measures would help store water during occasional flood events for gradual, managed use over time.

All of these diversification strategies reflect Osino’s acknowledgment that, in Namibia, water security can’t rely on a single source or a single plan.

Managing environmental risks

The ESIA is candid about the potential risks of such large-scale abstraction. Over-pumping could reduce groundwater levels, affect neighbouring boreholes, or damage dependent ecosystems. That’s why Osino’s consultants built mitigation commitments into the EMP: strict abstraction quotas aligned with sustainable yield estimates, regular groundwater level monitoring in both company and community boreholes, and adaptive pumping plans that can be dialled back if drawdown trends exceed safe limits.

Equally important is community consultation. The ESIA documents show that local stakeholders demanded detailed disclosure of pumping plans, monitoring results, and contingency measures. Osino pledged to establish ongoing communication forums to keep communities informed and involved in management decisions.

Balancing mining needs with local realities

Beyond Twin Hills, this ESIA provides a glimpse into the kind of planning that all mining in Namibia will require as water stress intensifies. Mining companies can no longer treat water as an unlimited input. Instead, they’ll face growing pressure—from regulators, communities, and investors alike—to show precisely how they’ll balance their own consumption with the needs of surrounding populations and ecosystems.

Osino’s approach, as laid out in the ESIA, is notable for recognising that balancing act. It proposes a combination of groundwater abstraction with sustainable yield limits, significant on-site recycling, and innovative reuse of treated wastewater. While no plan is risk-free, the layered strategy offers multiple lines of defence against over-extraction.

Of course, the proof will come in execution. Permits and modelling are only the start. Maintaining groundwater levels, building the pipeline responsibly, upgrading municipal wastewater treatment plants, and maintaining community trust will require ongoing attention and investment. Any slip in monitoring or transparency could erode the social license Osino is working to secure.

As Osino Resources pushes forward with its Twin Hills project, water will remain its most precious—and most scrutinised—resource.

The ESIA demonstrates that the company has conducted thorough research on sourcing, impact assessment, and stakeholder engagement. Now, the challenge is to turn plans on paper into real-world outcomes that keep both gold and water flowing—for the mine, and for everyone who calls this dry region home.


Share219Tweet137
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

November 7, 2026
Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

November 6, 2026
Teach farmers to co-exist with mining – parliamentary committee on Omaheke exploration

IAEA calls for more groundwater tests at Uranium One’s Wings project

November 6, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Subscribe now to receive all mining sector and related news!

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Extractor Magazine will use the information you provide on this form to be in touch with you and to provide updates and marketing.
Subscribe