    Core Energy seeks drilling contractor for maiden Barking Gecko uranium campaign

    Core Energy sets 2027 exploration horizon for Namibia uranium portfolio

    Keras puts US$3m behind entry into Namibia’s Kaoko copper belt

    Keras puts US$3m behind entry into Namibia’s Kaoko copper belt

    Arkle identifies extensive uranium system in maiden Namibia drilling

    Arkle identifies extensive uranium system in maiden Namibia drilling

    ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

    ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

    Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

    Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

    Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

    Deep Yellow advances Omahola, S-Bend and Tinkas alongside Tumas

    Deep Yellow spends N$600m on Tumas in 2026 financial year

    Deep Yellow spends N$600m on Tumas in 2026 financial year

    Deep Yellow builds Namibian base as local workforce reaches 45

    Deep Yellow builds Namibian base as local workforce reaches 45

    Unicorn targets Klein Aub copper production within 12 months

    Unicorn targets Klein Aub copper production within 12 months

    Ongwe launches 5,000m maiden drilling at Nguni gold prospect

    Ongwe launches 5,000m maiden drilling at Nguni gold prospect

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Gold

Bezant brings forward NLZM US$5m plant payment as Hope & Gorob targets September production

by Editor
August 28, 2026
in Gold
0
Bezant to seek permission to seal the Namib Lead deal
522
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Bezant Resources has agreed to accelerate the purchase of the processing plant being upgraded for its Hope & Gorob copper-gold project in Namibia, committing to a US$5 million payment by the end of October as it maintains a target of producing first concentrate by the end of September.

The agreement with CL US Minerals will bring Bezant closer to outright ownership of the former NLZM lead-zinc processing plant, now held under Tsaoxaub Metals, and give the company greater control over a facility it says could require about US$30 million and two years to replicate from scratch.

The plant is being upgraded and repurposed to process both copper sulphide and oxide pre-concentrate from Hope & Gorob, where mine development has been advancing towards first production.

Under the accelerated arrangement, Bezant will pay US$5 million by 31 October 2026, after which the vendor will release the security held under the original August 2025 share purchase agreement.

A further US$4.98 million will remain payable, taking the outstanding consideration covered by the new arrangement to US$9.98 million. The balance will not begin falling due until March 2029 and will be paid through quarterly instalments of US$415,000 until December 2031.

The structure effectively separates the immediate need to secure control of the plant from almost US$5 million in payments pushed several years into the future.

Bezant has also disclosed that an unnamed third party has expressed interest in co-investing towards the accelerated US$5 million payment. The company said arrangements were being finalised and could simplify its financing and security structure. However, it has not disclosed the identity of the prospective investor, the amount it may contribute or the terms of the proposed participation.

The financing is important because Bezant is simultaneously completing construction and commissioning work ahead of its September production target.

Executive chairman Colin Bird said the agreement would consolidate the corporate and financial arrangements surrounding Hope & Gorob and allow the company to secure control of the processing infrastructure earlier than previously envisaged.

“This agreement is a major step forward in the consolidation of the corporate and financial arrangements for the Hope & Gorob mining venture. The objective of ownership will be met sooner rather than later providing the Company with total control and the flexibility to consider further productivity improvements through further upgrades and increased throughput capacity,” Bird said.

“We are delighted with the progress being made and we remain on track to commence concentrate production by the end of September 2026. We will keep shareholders updated as we progress through completion of construction, commissioning and production,” he added.

The decision to accelerate ownership comes as Bezant reassesses the processing plant’s longer-term role following a recent increase in the mineral resource at Hope. The company now estimates that the initial Hope open pit alone could support a 35-year mine life.

That estimate excludes potential extensions of the Hope open pit and underground mineralisation, as well as drill-ready targets along 17 kilometres of strike within the mining licence. It also excludes the existing Gorob and Vendome mineral resources and exploration potential across licences containing more than 80 kilometres of prospective host rock.

The longer mine life is beginning to change the economics of the processing infrastructure. Bezant said its internal estimates and industry feedback indicate that developing a new plant with capacity comparable to the NLZM facility would require approximately US$30 million and about 24 months for regulatory approvals, construction and commissioning.

Securing the existing facility for substantially less than the estimated replacement cost therefore gives Bezant an alternative to building a new plant while leaving room to invest further in upgrades and higher throughput if Hope & Gorob supports larger production over time.

Bezant can also settle some or all of the US$4.98 million deferred consideration ahead of schedule, with early payments attracting a 12.5% annual discount.

CL US Minerals, meanwhile, has a 36-month option to convert up to £2 million of the deferred consideration into Bezant shares at £0.0013145 per share. Any shares issued under that arrangement would be subject to a two-month lock-up.

With the first concentrate still scheduled before the US$5 million accelerated payment becomes due, Bezant’s next test will be whether it can complete construction and commissioning, begin production by the end of September, and finalise the proposed third-party financing before the October payment deadline.

Share209Tweet131
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Core Energy seeks drilling contractor for maiden Barking Gecko uranium campaign

Core Energy sets 2027 exploration horizon for Namibia uranium portfolio

September 17, 2026
Osino Resources on track to employ 1 000 Namibians at Twin Hills Gold Project

Shandong Gold Mining says Twin Hills gold mine to cost N$8.9bn

September 17, 2026
Keras puts US$3m behind entry into Namibia’s Kaoko copper belt

Keras puts US$3m behind entry into Namibia’s Kaoko copper belt

September 16, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In