    Midas kicks off major drill campaign at Otavi Copper Project

    Midas finds multiple high-grade copper zones at Deblin near Otavi

    Serval confirms copper mineralisation in Namibia’s Kaoko Basin

    Serval allocates US$7.1m to Namibia copper exploration

    Madison Metals starts drilling at Khan Project in Namibia

    Critical One plans Critical Two Energy for Namibian uranium assets after failed US$3.5m sale

    Skeleton Coast Uranium closes N$95m funding, completes Namibia licence deal

    Skeleton Coast commits N$13.75m to uranium exploration near Langer Heinrich

    Higher uranium prices cushion 19% production drop at Langer Heinrich

    Higher uranium prices cushion 19% production drop at Langer Heinrich

    Arkle brings forward second uranium target after encouraging Namibia drilling

    Arkle finds uranium along 2.9km stretch near Trekkopje

    Keras becomes Okopa after securing 51% stake in Cornerstone Mining

    Keras becomes Okopa after securing 51% stake in Cornerstone Mining

    Noronex sees Powerline drill campaign as key toward commercial-scale discovery

    Noronex exits DorWit, its first Namibian copper projects

    Kaoko opens second Chalkos drill front along 800m Donkey Hill outcrop

    Kaoko’s first Chalkos drilling returns individual sample grading 6.42% copper

    Why Elizabeth Bay keeps coming back from the dead

    Why Elizabeth Bay keeps coming back from the dead

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Namibia Construction and Nexus Building win A$34 million Tumas contracts

by Editor
July 20, 2026
in Uranium
0
Namibia Construction and Nexus Building win A$34 million Tumas contracts
542
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Deep Yellow has taken another significant step towards developing its flagship Tumas uranium project in Namibia by awarding two major civil and concrete construction contracts worth a combined A$34 million, signalling growing confidence that the project is moving steadily towards a final investment decision later this year.

The contracts, announced on 16 July, have been awarded to Namibia Construction Pty Ltd and Nexus Building and Civils Contractors Pty Ltd, both 100% Namibian-owned companies, following a competitive tender process.

Mobilisation is scheduled to begin in August 2026, allowing construction activities to advance toward the company’s targeted final investment decision (FID) in the fourth quarter of 2026.

Although Deep Yellow stressed that the awards do not constitute a decision to build the mine, they form part of a deliberate strategy to reduce execution risk by securing critical construction capability before the project enters its full development phase.

The approach is intended to ensure that once the board gives formal approval to proceed, major construction work can begin without unnecessary delays.

The larger of the two contracts, valued at approximately A$18.5 million, was awarded to Namibia Construction.

The company will undertake reinforced concrete works within the beneficiation, leach feed thickening, and tailings transfer facilities; fabricate and install precast concrete elements across the processing plant; and construct the reinforced earth retaining wall supporting the run-of-mine stockpile.

The second contract, worth about A$15.5 million, was awarded to Nexus Building and Civils Contractors. Its scope includes construction of reinforced concrete foundations, plinths, slabs and associated embedded infrastructure throughout the balance of the processing plant.

Deep Yellow Managing Director and Chief Executive Officer Greg Field said the awards reflected the company’s long-standing strategy of progressively removing project risks before committing to construction.

“These awards represent another important milestone in our disciplined approach to project development. Our objective has always been to systematically remove execution risk, secure high-quality contractors and ensure the Project is positioned for efficient delivery as we advance toward FID towards the end of this year,” Field said.

He noted that civil and concrete works underpin every major processing facility and securing contractors at this stage would allow multiple construction work fronts to operate simultaneously once development begins, improving flexibility and confidence in project delivery.

Equally significant is Deep Yellow’s decision to award both contracts to Namibian companies.

The company said the works are expected to be carried out predominantly by Namibian employees, reinforcing its commitment to local content and ensuring more of the economic benefits generated by the Tumas project remain within the country.

“Developing Tumas in partnership with local industry is central to our strategy and reflects our commitment to delivering long-term value for Namibia alongside our shareholders,” Field said.

The contract awards represent another milestone in Deep Yellow’s phased development strategy, which has seen the company progressively secure engineering, procurement and construction packages while continuing technical optimisation work ahead of FID.

By awarding key contracts before construction formally begins, the company is attempting to shorten the time between board approval and project execution without altering the planned 24-month construction schedule.

The announcement also provides another indication that Tumas remains one of Namibia’s most advanced undeveloped uranium projects.

If the final investment decision proceeds as expected in the fourth quarter of 2026, the project will become one of the country’s next uranium mines, adding to Namibia’s expanding production pipeline at a time when global demand for nuclear fuel continues to strengthen.

Share217Tweet136
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Midas kicks off major drill campaign at Otavi Copper Project

Midas finds multiple high-grade copper zones at Deblin near Otavi

October 15, 2026
Serval confirms copper mineralisation in Namibia’s Kaoko Basin

Serval allocates US$7.1m to Namibia copper exploration

October 14, 2026
Japan’s 50% Lofdal stake awaits final approvals

Lofdal’s 50% Japanese ownership deal delayed another 30 days

October 14, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In