    Unicorn draws £1.25m to advance Klein Aub copper mine acquisition

    Unicorn draws £1.25m to advance Klein Aub copper mine acquisition

    Core Energy seeks drilling contractor for maiden Barking Gecko uranium campaign

    Core Energy sets 2027 exploration horizon for Namibia uranium portfolio

    Keras puts US$3m behind entry into Namibia’s Kaoko copper belt

    Keras puts US$3m behind entry into Namibia’s Kaoko copper belt

    Arkle identifies extensive uranium system in maiden Namibia drilling

    Arkle identifies extensive uranium system in maiden Namibia drilling

    ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

    ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

    Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

    Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

    Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

    Deep Yellow advances Omahola, S-Bend and Tinkas alongside Tumas

    Deep Yellow spends N$600m on Tumas in 2026 financial year

    Deep Yellow spends N$600m on Tumas in 2026 financial year

    Deep Yellow builds Namibian base as local workforce reaches 45

    Deep Yellow builds Namibian base as local workforce reaches 45

    Unicorn targets Klein Aub copper production within 12 months

    Unicorn targets Klein Aub copper production within 12 months

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Graphite

Northern Graphite completes 85km relocation of Okanjande graphite processing plant

by Editor
June 30, 2026
in Graphite
0
Northern Graphite keeps Okanjande ready for restart
515
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Northern Graphite has completed the relocation of its graphite processing plant from the former Okorusu Mine to the Okanjande Mine in Namibia, marking the first major construction milestone in the planned restart of graphite production.

The Canadian graphite producer announced on Tuesday that the processing equipment had been successfully dismantled at Okorusu and transported approximately 85 kilometres to the fully permitted Okanjande Mine, where it will now be reassembled ahead of the planned restart of mining and processing operations in late 2027, subject to financing.

The company said the relocation was completed safely, on schedule and without incident.

Northern Graphite chief executive Hugues Jacquemin described the move as a significant step in advancing the company’s mine-to-battery strategy.

“The completion of the relocation is a major milestone for Northern and demonstrates our ability to execute as we advance the restart of production at Okanjande,” Jacquemin said.

“With plant equipment now in place at the mine site, we are advancing preparations for production and strengthening the foundation for supplying our planned joint venture BAM facility in Yanbu, Kingdom of Saudi Arabia, which is targeted for initial production in 2028 as part of Northern’s broader mine-to-battery strategy.”

The relocation follows a Preliminary Economic Assessment completed in 2023, which concluded that moving the processing plant to Okanjande would be more economical than refurbishing the existing processing facility at Okorusu.

By relocating the plant to the mine site, Northern expects to eliminate the need to transport graphite ore over long distances for processing, reducing haulage costs, fuel consumption and greenhouse gas emissions. The company also plans to incorporate solar power and dry tailings technology to improve water efficiency and reduce the project’s environmental footprint.

The completion of the relocation significantly de-risks the restart project by placing the key processing infrastructure at the mine site, allowing the company to focus on plant reassembly, commissioning and financing over the coming months.

Okanjande, which is currently in care and maintenance, is one of Africa’s largest permitted graphite projects and forms part of Northern’s strategy to establish an integrated mine-to-battery materials business supplying both traditional industrial markets and the rapidly expanding lithium-ion battery sector.

Jacquemin said the project’s location further strengthens its competitiveness.

“Okanjande hosts a large graphite resource in one of Africa’s most politically stable jurisdictions, with access to a deep-water port that provides substantial competitive advantages over many competing projects.

“Completing the plant relocation further de-risks the restart strategy and positions Northern to move quickly to support secure graphite supply chains independent of China.”

The reassembled processing plant is expected to supply graphite concentrate for Northern’s planned battery anode materials joint venture in Yanbu, Saudi Arabia, which is targeted to begin production in 2028 as the company expands its global mine-to-battery value chain.

Share206Tweet129
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Langer Heinrich builds boundary wall for Usakos school

Langer Heinrich builds boundary wall for Usakos school

September 18, 2026
Sultan Resources allocates N$13.3m to kickstart Namibia’s Damara Gold Project

Sultan applies for an additional 171 km² copper-gold ground in Kalkfeld

September 18, 2026
Unicorn draws £1.25m to advance Klein Aub copper mine acquisition

Unicorn draws £1.25m to advance Klein Aub copper mine acquisition

September 17, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In