    Nandi-Ndaitwah proposes Angola-Namibia-South Africa power corridor

    Nandi-Ndaitwah proposes Angola-Namibia-South Africa power corridor

    Arkle brings forward second uranium target after encouraging Namibia drilling

    Arkle brings forward second uranium target after encouraging Namibia drilling

    ReconAfrica penetrates 400m hydrocarbon interval at Kavango West 1X

    ReconAfrica records first onshore hydrocarbon flow during Namibia production test

    Pancontinental sees over 20 billion barrels recoverable at PEL 87

    Pancontinental launches feasibility study to improve PEL 87 seismic data processing

    Noronex launches 7,000m drilling campaign at Powerline Copper Project on Kalahari Copper Belt

    South32 backs expanded copper hunt across Noronex’s Namibian projects

    Elevate now owns 90% stake in Marenica uranium project

    Elevate now owns 90% stake in Marenica uranium project

    Golden Deeps uncovers bonanza-grade copper and silver beneath Graceland gossans near Tsumeb

    Golden Deeps to test three-deep sulphide targets at Graceland prospect in Otavi

    Noronex launches 7,000m drilling campaign at Powerline Copper Project on Kalahari Copper Belt

    Noronex plans 2,500m Namibia copper drill programme for 2026/27

    Connected Minerals seeks A$4.5m to accelerate Namibia uranium exploration

    Connected Minerals seeks A$4.5m to accelerate Namibia uranium exploration

    Former Namcor executive Nakashole now Galp deputy country manager for public and ops affairs

    Former Namcor executive Nakashole now Galp deputy country manager for public and ops affairs

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Graphite

Northern Graphite completes 85km relocation of Okanjande graphite processing plant

by Editor
June 30, 2026
in Graphite
0
Northern Graphite keeps Okanjande ready for restart
509
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Northern Graphite has completed the relocation of its graphite processing plant from the former Okorusu Mine to the Okanjande Mine in Namibia, marking the first major construction milestone in the planned restart of graphite production.

The Canadian graphite producer announced on Tuesday that the processing equipment had been successfully dismantled at Okorusu and transported approximately 85 kilometres to the fully permitted Okanjande Mine, where it will now be reassembled ahead of the planned restart of mining and processing operations in late 2027, subject to financing.

The company said the relocation was completed safely, on schedule and without incident.

Northern Graphite chief executive Hugues Jacquemin described the move as a significant step in advancing the company’s mine-to-battery strategy.

“The completion of the relocation is a major milestone for Northern and demonstrates our ability to execute as we advance the restart of production at Okanjande,” Jacquemin said.

“With plant equipment now in place at the mine site, we are advancing preparations for production and strengthening the foundation for supplying our planned joint venture BAM facility in Yanbu, Kingdom of Saudi Arabia, which is targeted for initial production in 2028 as part of Northern’s broader mine-to-battery strategy.”

The relocation follows a Preliminary Economic Assessment completed in 2023, which concluded that moving the processing plant to Okanjande would be more economical than refurbishing the existing processing facility at Okorusu.

By relocating the plant to the mine site, Northern expects to eliminate the need to transport graphite ore over long distances for processing, reducing haulage costs, fuel consumption and greenhouse gas emissions. The company also plans to incorporate solar power and dry tailings technology to improve water efficiency and reduce the project’s environmental footprint.

The completion of the relocation significantly de-risks the restart project by placing the key processing infrastructure at the mine site, allowing the company to focus on plant reassembly, commissioning and financing over the coming months.

Okanjande, which is currently in care and maintenance, is one of Africa’s largest permitted graphite projects and forms part of Northern’s strategy to establish an integrated mine-to-battery materials business supplying both traditional industrial markets and the rapidly expanding lithium-ion battery sector.

Jacquemin said the project’s location further strengthens its competitiveness.

“Okanjande hosts a large graphite resource in one of Africa’s most politically stable jurisdictions, with access to a deep-water port that provides substantial competitive advantages over many competing projects.

“Completing the plant relocation further de-risks the restart strategy and positions Northern to move quickly to support secure graphite supply chains independent of China.”

The reassembled processing plant is expected to supply graphite concentrate for Northern’s planned battery anode materials joint venture in Yanbu, Saudi Arabia, which is targeted to begin production in 2028 as the company expands its global mine-to-battery value chain.

Share204Tweet127
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Nandi-Ndaitwah proposes Angola-Namibia-South Africa power corridor

Nandi-Ndaitwah proposes Angola-Namibia-South Africa power corridor

July 17, 2026
Arkle brings forward second uranium target after encouraging Namibia drilling

Arkle brings forward second uranium target after encouraging Namibia drilling

July 17, 2026
ReconAfrica penetrates 400m hydrocarbon interval at Kavango West 1X

ReconAfrica records first onshore hydrocarbon flow during Namibia production test

July 16, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In