    Bannerman says Etango passes key construction milestones as workforce tops 560

    Bannerman says Etango passes key construction milestones as workforce tops 560

    Celsius Resources in early-stage discussions for possible partnership for Opuwo Cobalt Project

    Aluminium Corporation of China agrees to acquire Opuwo cobalt-copper project in US$15 million deal

    New Haib Copper Project indicated and inferred estimates show decrease in tonnage but increase in value

    Koryx reports 714m copper intercept at Haib

    Midas Minerals prepares to transition copper assets to full scale drilling

    Maiden Deblin drill hole intersects 57m of visible copper mineralisation in Namibia

    Arkle set to drill after confirming uranium across Erongo targets

    Arkle set to drill after confirming uranium across Erongo targets

    Namibia approves Prime Global’s entry into Tower Resources’ offshore licence

    Namibia approves Prime Global’s entry into Tower Resources’ offshore licence

    South Korean Hanwha Ocean and SBM Offshore emerge as frontrunners for Venus oil development’s $10bn Venus FPSO

    South Korean Hanwha Ocean and SBM Offshore emerge as frontrunners for Venus oil development’s $10bn Venus FPSO

    MUN embarks on nationwide engagement with workers

    MUN embarks on nationwide engagement with workers

    Serval targets first drilling at Omatapati copper-silver prospect in Kaoko Basin

    Serval targets first drilling at Omatapati copper-silver prospect in Kaoko Basin

    Eco Atlantic says Orange Basin oil discoveries open farm-out opportunities for its Walvis Basin blocks

    Eco Atlantic prepares major offshore exploration campaign across three Walvis Basin licences

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Bannerman says Etango passes key construction milestones as workforce tops 560

by Editor
June 30, 2026
in Uranium
0
Bannerman says Etango passes key construction milestones as workforce tops 560
491
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

 

Bannerman Energy says construction of its Etango uranium project outside Swakopmund remains on schedule and within budget, with major early works nearing completion as the company moves closer to full-scale mine construction.

According to the company’s latest construction update, the bulk earthworks contract is now about 92% complete, while more than 560 workers are on site, collectively achieving over 1.1 million lost-time injury-free hours since work began.

The project has also reached several major construction milestones. Approximately 10,800 cubic metres of concrete have now been poured, representing around 60% completion of the Phase 1 and Phase 2A concrete packages. Permanent processing infrastructure, including the primary crusher, stockpile tunnel, secondary and tertiary crushing facilities and the fine ore silo, is beginning to emerge across the site.

Managing director Gavin Chamberlain said the progress had significantly reduced execution risk ahead of the main construction phase.

“Our key contract partners continue to deliver across the Etango site. Of particular note is that the 24-month bulk earthworks contract is now more than 90% complete, a substantial achievement and a key investment in derisking the critical path for full-scale construction of the Etango Project,” he said.

Bannerman said detailed engineering is also advancing steadily. Civil and mechanical design for the dry plant is about 94% complete, while engineering work on the wet plant remains on schedule for construction drawings to be issued later this year.

Supporting infrastructure is progressing alongside construction. The company has signed a permanent water supply agreement with NamWater, while installation of the first phase of the water pipeline is approximately 87% complete. A definitive power supply agreement has also been concluded with NamPower, and detailed design work continues on the acid storage and handling facility at the Port of Walvis Bay.

Bannerman said local content remains a key focus, noting that all contractors currently working on the project are Namibian companies. Several construction packages, including the gatehouse, have been subcontracted to locally owned small and medium enterprises to broaden participation in the mine’s development.

The Etango-8 development is designed to produce an average of 3.5 million pounds of uranium oxide annually over an initial 15-year mine life.

Share196Tweet123
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Bannerman says Etango passes key construction milestones as workforce tops 560

Bannerman says Etango passes key construction milestones as workforce tops 560

June 30, 2026
Celsius Resources in early-stage discussions for possible partnership for Opuwo Cobalt Project

Aluminium Corporation of China agrees to acquire Opuwo cobalt-copper project in US$15 million deal

June 30, 2026
New Haib Copper Project indicated and inferred estimates show decrease in tonnage but increase in value

Koryx reports 714m copper intercept at Haib

June 29, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In