    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas intersects 9.83% copper at Otavi’s Hartbeespoort prospect

    Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

    Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

    Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

    Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

    Teach farmers to co-exist with mining – parliamentary committee on Omaheke exploration

    IAEA calls for more groundwater tests at Uranium One’s Wings project

    Skeleton Coast Uranium raises C$2.3 million for Namibia exploration

    Skeleton Coast Uranium raises C$2.3 million for Namibia exploration

    Paladin’s Namibia after-tax profit rises from US$1.8m to US$8.1m in September quarter

    Paladin’s Namibia after-tax profit rises from US$1.8m to US$8.1m in September quarter

    Langer Heinrich uranium revenue jumps 71% to US$304m

    Paladin banks on J Pit to meet 5.1 million to 5.6 million pound uranium target at Langer Heinrich

    Nandi-Ndaitwah says bureaucracy nearly cost Namibia US$2.5 billion Dangote investment

    Nandi-Ndaitwah says bureaucracy nearly cost Namibia US$2.5 billion Dangote investment

    Dangote wants more investment opportunities in Namibia after US$2.5 billion commitment

    Dangote wants more investment opportunities in Namibia after US$2.5 billion commitment

    Swakop Uranium plans three-pit uranium mine on 130 km² in Erongo

    Swakop Uranium plans three-pit uranium mine on 130 km² in Erongo

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Elevate grows Marenica uranium resource from 40.2Mlb to 52.8Mlb

by Editor
June 10, 2026
in Uranium
0
Elevate grows Marenica uranium resource from 40.2Mlb to 52.8Mlb
538
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Elevate Uranium Limited has increased the mineral resource at its Marenica Uranium Project in Namibia from approximately 40.2 million pounds to 52.8 million pounds of uranium oxide following a major infill drilling programme completed during 2026.

The latest drilling campaign added 12.6 million pounds of contained uranium oxide, representing a 31% increase in contained metal since the company’s February 2026 resource update.

The updated JORC-compliant mineral resource estimate now stands at 45.3 million tonnes grading 180 parts per million uranium oxide (U3O8), positioning Marenica among the larger undeveloped uranium projects in Namibia’s Erongo Region.

Elevate said the latest increase follows the February 2026 resource re-evaluation, which effectively doubled the project grade after the company comprehensively reprocessed historical geological and radiometric datasets.

The company’s total Namibian uranium inventory has now grown to 116 million pounds U3O8, while Elevate’s global uranium resource base stands at approximately 173 million pounds U3O8.

Managing director Murray Hill said Marenica was now advancing steadily toward future feasibility studies as both drilling and metallurgical programmes accelerate simultaneously.

“In February we reported a resource that had essentially doubled in grade following a comprehensive reanalysis of our historical dataset. Now, with targeted infill drilling of the areas we identified as growth targets at the time, we have added a further 12.6 Mlb to bring the total to 52.8 Mlb at a grade of 180 ppm U3O8,” Hill said.

“The resource is growing methodically and with improving confidence.”

The company currently has four drill rigs operating at Marenica as it works to convert inferred resources into indicated resources, which are required to support future financial modelling and feasibility studies.

Bulk samples excavated from multiple zones across the project area are also being processed through Elevate’s Namibian U-pgrade™ pilot plant programme during 2026.

The company said the pilot plant work is expected to generate definitive metallurgical and processing inputs required for future development studies.

Elevate originally developed its proprietary U-pgrade™ beneficiation technology using ore from the Marenica deposit itself, with the current programme now testing material from across the expanded resource footprint.

At a 100 parts per million cut-off grade, the updated resource includes 16.8 million tonnes grading 205 parts per million U3O8 in the indicated category, together with 28.5 million tonnes grading 175 parts per million U3O8 in the inferred category, for a combined 45.3 million tonnes grading 180 parts per million U3O8 containing 52.8 million pounds U3O8.

The resource remains robust across multiple cut-off grades. At a higher 200 parts-per-million cut-off, Marenica still hosts approximately 21.7 million pounds of U3O8 grading 340 parts per million.

Elevate said the Marenica deposit extends approximately nine kilometres north-to-south and up to nine kilometres east-to-west, with mineralisation reaching depths greater than 100 metres in some northern sections of the project.

The uranium mineralisation is hosted within two main geological environments. Palaeochannel calcrete mineralisation contains approximately 38.6 million pounds U3O8, while weathered basement-hosted mineralisation contains roughly 14.2 million pounds U3O8.

According to the company, uranium occurs mainly as carnotite, formed through groundwater precipitation processes similar to those in several other calcrete-hosted uranium systems in Namibia.

Elevate also noted that the nearby Trekkopje uranium project, owned by Orano, advanced to pilot plant stage using comparable geological mineralisation systems.

The updated estimate is based on an extensive drilling database comprising 3,874 drill holes, totalling approximately 89,850 metres, completed by reverse-circulation, air-core, rotary air-blast, and diamond drilling methods.

The company said portions of the deposit have now been drilled at 40-metre by 40-metre spacing, with some higher-confidence zones infilled to 20-metre by 20-metre spacing as Elevate works toward future mine planning and feasibility assessments.

Elevate said the Marenica Project forms part of its broader Central Erongo uranium portfolio alongside the Koppies Project, with both projects supporting a potential district-scale uranium development strategy built around the U-pgrade™ processing technology.

Share215Tweet135
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

Midas intersects 9.83% copper at Otavi’s Hartbeespoort prospect

November 9, 2026
Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

Nandi-Ndaitwah acknowledges communication gaps over petroleum plans

November 7, 2026
Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

Eastport uncovers copper and gold mineralisation at Matsitama in Botswana

November 6, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Subscribe now to receive all mining sector and related news!

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Extractor Magazine will use the information you provide on this form to be in touch with you and to provide updates and marketing.
Subscribe