    Kaoko opens second Chalkos drill front along 800m Donkey Hill outcrop

    Kaoko’s first Chalkos drilling returns individual sample grading 6.42% copper

    Why Elizabeth Bay keeps coming back from the dead

    Why Elizabeth Bay keeps coming back from the dead

    Australian company Gibb River Diamonds acquires greenfield uranium projects in Erongo and Kunene

    Permit uncertainty pushes Gibb out of Namibia uranium exploration

    Skeleton Coast Uranium seeks C$5m for Namibia exploration

    Skeleton Coast Uranium seeks C$5m for Namibia exploration

    Serval confirms copper mineralisation in Namibia’s Kaoko Basin

    Serval confirms 37.8% copper and 573g/t silver at Kaoko Basin

    Koryx hits 969m at 0.27% copper equivalent at Haib

    Haib lifts processing capacity to 48Mtpa as Koryx targets November PFS

    Forsys’ Norasa in the making

    Asarian approves 4,500m Namibplaas drilling programme to upgrade 41.1Mlb uranium resource

    Elizabeth Bay Mine in trouble again

    US$50m investment targets restart of Elizabeth Bay diamond mine

    Andrada finds high-grade lithium beyond the main Lithium Ridge trend

    Andrada finds high-grade lithium beyond the main Lithium Ridge trend

    Eureka gets N$12.9m development funding push

    ReeXploration plans Phase 2 drilling after a 16.7 m uranium hit at Eureka

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Gold

Wia enters 2026 with N$555m war chest as Kokoseb gold project advances toward DFS milestone

by Editor
January 21, 2026
in Gold
0
Kokoseb mine life set at 11+ years producing 177,000 ounces first 5 years
554
SHARES
1.6k
VIEWS
Share on FacebookShare on Twitter

Wia Gold entered 2026 with a strong balance sheet, holding A$45.84 million in cash, equivalent to about N$555 million, and no debt at the end of December, as the company accelerated work to convert the Kokoseb Gold Project from a large-scale discovery into a fully defined development in central Namibia.

The solid cash position underpinned an intensive December quarter in which Wia advanced the Definitive Feasibility Study on Kokoseb, expanded drilling across high-grade zones and moved key permitting processes forward.

The quarter followed completion of the Kokoseb Scoping Study in September 2025 and marked a clear shift from concept validation toward execution planning, with DFS completion targeted for the second half of calendar year 2026.

Kokoseb, which hosts a mineral resource of 2.93 million ounces of gold, remains the company’s sole strategic focus after the divestment of non-core assets in Côte d’Ivoire.

Management said the period was dedicated to de-risking the project technically, environmentally and commercially, while building the foundations for a potential mine development decision.

Progress on the DFS was recorded across all major workstreams. Geotechnical drilling for the open pit and potential underground operation is well advanced, with completion expected in February 2026 before samples are dispatched to South Africa for laboratory testing.

Mining studies also moved forward during the quarter, with expressions of interest issued for contract mining budget pricing and strong responses received from industry participants.

Metallurgical testwork is substantially complete and is now undergoing validation ahead of final integration into the DFS.

On the processing side, Wia appointed Senet, a subsidiary of DRA, to undertake process plant design and cost estimation. Site geotechnical investigations for the plant have been completed, while the basis of design for non-process infrastructure, including buildings and earthworks, has been finalised.

Water supply, a critical factor for any large mining development in Namibia, continued to receive focused attention.

Exploratory drilling and pump testing were completed at the Okombahe Water Supply Scheme, with hydrogeological modelling scheduled to commence imminently.

Drilling at the Ozondati Water Supply Scheme is expected to start toward the end of January 2026, while mobilisation of audio magnetotelluric equipment is underway to support broader geophysical surveys.

Power supply studies also reached an important milestone during the quarter, with NamPower completing its internal power supply assessments.

The results of these studies are expected to be delivered to Wia in the first quarter of 2026 and will inform final infrastructure and cost assumptions within the DFS.

Alongside study work, Wia maintained an aggressive exploration campaign at Kokoseb aimed at confirming the continuity of high-grade mineralisation and testing depth extensions that could support a future underground operation.

Six drill rigs remain active on site, focused on both resource conversion and expansion as the company works to further strengthen the quality of the resource base.

Drilling results released during the quarter delivered multiple high-grade intercepts that reinforced the project’s underground potential, demonstrating that mineralisation remains open at depth and continues along plunging shoots previously identified within the deposit.

Management has consistently highlighted this underground optionality as a key longer-term value driver beyond the planned open-pit operation.

Beyond the core Kokoseb area, regional reconnaissance programmes continued across Wia’s broader Namibian licence package.

These activities, including stream sediment sampling, reconnaissance mapping and rock-chip sampling, are designed to fast-track decisions on whether to pursue more systematic exploration programmes that could complement the Kokoseb development.

Permitting advanced steadily during the quarter, with the Mining Licence application already lodged with the mines ministry in October 2025.

The Environmental and Social Impact Assessment is nearing completion, with final stakeholder review scheduled for early 2026 and submission to regulators expected in the first quarter of the year.

Strategically, the December quarter also marked Wia’s exit from Côte d’Ivoire. In November 2025, the company entered into a binding agreement to divest its non-core West African exploration assets to ASX-listed Santa Fe Minerals.

The transaction, structured through a combination of equity and performance rights, allows Wia to concentrate capital and management attention on Kokoseb while retaining exposure to potential upside through an ongoing shareholding in Santa Fe.

The Kokoseb Scoping Study completed in September 2025 continues to underpin the project’s investment case. It outlines an initial mine life of more than 11 years, average production of about 180,000 ounces per annum in the first five years from an open-pit operation, and strong project economics at both consensus and prevailing gold prices.

Corporate changes are set to shape the next phase of development. Highly experienced mining executive Henk Diederichs will assume the role of managing director and chief executive officer from 1 February 2026, with Josef El-Raghy transitioning from executive to non-executive chairman as the company moves toward the critical development phase at Kokoseb.

Share222Tweet139
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Kaoko opens second Chalkos drill front along 800m Donkey Hill outcrop

Kaoko’s first Chalkos drilling returns individual sample grading 6.42% copper

October 12, 2026
Midas Otavi Copper Project acquisition cleared

Midas extends Spaatzu to 1.5km with grades of up to 2.39%

October 12, 2026
Arcadia finds funding partners for Swanson Tantalum Mine

Arcadia turns to European financiers as Swanson-Xinhai deal remains unresolved

October 10, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In