• Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
Sunday, August 16, 2026
  • Login
The Extractor Magazine
  • Home
  • News
    • All
    • Africa
    • Biofuels
    • Climate
    • Copper
    • Exploration
    • Lithium
    • Minerals
    • Mining
    • Namibia
    • Nickel
    • Oil & Gas
    • Precious Metals
    • RIGS & VESSELS
    • Silver
    • Uranium
    Quantum Leap Energy plans nuclear fuel processing pilot plant at Walvis Bay

    Quantum Leap Energy plans nuclear fuel processing pilot plant at Walvis Bay

    Koryx nears end of Haib infill drilling as resource update looms

    Koryx nears end of Haib infill drilling as resource update looms

    John Borshoff leaves behind a US$6b legacy in Namibia and Malawi

    Forsys becomes Asarian Energy, targets uranium expansion beyond Namibia

    Union warns workers risk being left behind as mining changes

    Union warns workers risk being left behind as mining changes

    Midas takes 6 months from acquisition to drilling

    Midas hits 35.6m at 3.35% copper at Deblin near Otavi

    Namibia’s next mines depend on today’s exploration – Dr Gabi Schneider

    Namibia’s next mines depend on today’s exploration – Dr Gabi Schneider

    Kaoko Metals begins maiden drilling at Namibia’s Chalkos copper-silver project

    Kaoko Metals begins maiden drilling at Namibia’s Chalkos copper-silver project

    Sandpiper phosphate project cleared environmentally after decade-long battle

    Sandpiper phosphate project cleared environmentally after decade-long battle

    Appian makes Namibia its biggest global mining investment destination

    Namibia must develop more investment-ready mining projects, says Appian

    Koryx says Haib redesign has strengthened case for about US$1.6 billion development

    Koryx says Haib redesign has strengthened case for about US$1.6 billion development

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Langer Heinrich Mine hits 3 million pounds output as final ramp-up phase begins

by Editor
August 28, 2025
in Uranium
0
Langer Heinrich Mine hits 3 million pounds output as final ramp-up phase begins
515
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

The Langer Heinrich Mine has reported its strongest operational results since restarting production, delivering 993,843 pounds of U₃O₈ in the June 2025 quarter—a 33% increase over the previous quarter.

This brings the total FY2025 output to 3.0 million pounds of U₃O₈, the highest since the mine’s restart.

The performance was driven by record crusher throughput of 1.17 million tonnes, surpassing a decade-old benchmark, consistent plant performance, and improved feed blend quality.

Processing plant recoveries averaged 87 per cent, the highest in the mine’s history, with improvements expected to be sustained into FY2026.

Sales for the quarter reached 710,051 pounds, contributing to 2.7 million pounds sold in FY2025.

One new contract was signed, bringing Langer Heinrich Mine’s agreements to 13 tier-one customers across the US, Europe, and Asia.

In total, £ 24.1 million is contracted through 2030, with 86 per cent of reserves exposed to market-related pricing or uncontracted, ensuring long-term revenue upside.

A life-of-mine agreement remains in place with China’s CNNC, one of the world’s largest uranium consumers.

Financially, quarterly revenue stood at US$39.4 million (approximately N$709 million), while full-year 2025 revenue was US$177.7 million (approximately N$3.19 billion).

The average realised price was US$65.7 per pound (N$1,182/lb) for the year.

Cost of sales totalled US$183.7 million (N$3.31 billion), with a quarterly cost of production of US$37.5 per pound (N$675/lb), reflecting efficiencies from higher output.

The final phase of the ramp-up is now underway, with approximately 50 per cent of the mining fleet expected to be operational by June 2025.

The remaining fleet is scheduled for delivery later this year and expected to be fully commissioned in the second half of FY2026.

Langer Heinrich Mine aims to achieve full mining and processing capacity by the end of fiscal year 2027.

The mine plan has been optimised to prioritise medium and high-grade ore for processing, with lower-grade material stockpiled for future treatment.

Exploration and optimisation drilling continued within the ML140 mining lease, strengthening geological confidence in near-term mining areas.

Capital expenditure was focused on the construction of Tailings Storage Facility 6 (TSF6), while a US$19.9 million (N$358 million) impairment on low-grade ore stockpiles was recognised earlier in the year.

Share206Tweet129
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Kokoseb plans 130km desalinated water pipeline from Trekkopje

Kokoseb plans 130km desalinated water pipeline from Trekkopje

August 15, 2026
Quantum Leap Energy plans nuclear fuel processing pilot plant at Walvis Bay

Quantum Leap Energy plans nuclear fuel processing pilot plant at Walvis Bay

August 15, 2026
Sprott’s Nam exposure set to reach US$432.5m

Sprott’s Nam exposure set to reach US$432.5m

August 15, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In