• Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
Thursday, October 15, 2026
  • Login
The Extractor Magazine
  • Home
  • News
    • All
    • Africa
    • Biofuels
    • Climate
    • Copper
    • Exploration
    • Lithium
    • Minerals
    • Mining
    • Namibia
    • Nickel
    • Oil & Gas
    • Precious Metals
    • RIGS & VESSELS
    • Silver
    • Uranium
    Midas kicks off major drill campaign at Otavi Copper Project

    Midas finds multiple high-grade copper zones at Deblin near Otavi

    Serval confirms copper mineralisation in Namibia’s Kaoko Basin

    Serval allocates US$7.1m to Namibia copper exploration

    Madison Metals starts drilling at Khan Project in Namibia

    Critical One plans Critical Two Energy for Namibian uranium assets after failed US$3.5m sale

    Skeleton Coast Uranium closes N$95m funding, completes Namibia licence deal

    Skeleton Coast commits N$13.75m to uranium exploration near Langer Heinrich

    Higher uranium prices cushion 19% production drop at Langer Heinrich

    Higher uranium prices cushion 19% production drop at Langer Heinrich

    Arkle brings forward second uranium target after encouraging Namibia drilling

    Arkle finds uranium along 2.9km stretch near Trekkopje

    Keras becomes Okopa after securing 51% stake in Cornerstone Mining

    Keras becomes Okopa after securing 51% stake in Cornerstone Mining

    Noronex sees Powerline drill campaign as key toward commercial-scale discovery

    Noronex exits DorWit, its first Namibian copper projects

    Kaoko opens second Chalkos drill front along 800m Donkey Hill outcrop

    Kaoko’s first Chalkos drilling returns individual sample grading 6.42% copper

    Why Elizabeth Bay keeps coming back from the dead

    Why Elizabeth Bay keeps coming back from the dead

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Deep Yellow advances Tumas’ readiness as it builds toward production

by Editor
July 24, 2025
in Uranium
0
Deep Yellow’s share purchase plan oversubscribed by N$182m
525
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Deep Yellow Limited is translating its conceptual Operational Readiness Plan (ORP) into a fully developed implementation framework.

The plan is now being fleshed out with detailed policies, procedures, and human resource structures aimed at ensuring the smooth commissioning and eventual operation of the Tumas uranium plant.

With a team boasting deep operational experience and long-standing roots in Namibia, Deep Yellow is positioning itself for a seamless transition from development to production.

De-risking for decision day

The work on operational readiness forms part of a broader strategy to de-risk the Tumas Project ahead of a Final Investment Decision (FID).

However, Deep Yellow has put the decision on hold, stating that FID will proceed only once uranium prices improve to support favourable project economics.

In the meantime, engineering, procurement, and early site works are all tracking on schedule, ensuring that the project will be ready to advance swiftly when market conditions allow.

Final mine scheduling, built on the results of a comprehensive grade control drilling campaign, is currently underway.

The findings from that program are being integrated to refine the Ore Reserve Estimate and optimise the tailings storage facility design.

Meanwhile, the re-costing of reagents and consumables is helping to fine-tune the project’s economic profile, while negotiations with prequalified mining contractors are entering their final stage.

Once contracts are signed, pre-production mining can begin in earnest.

Engineering and construction on track

Engineering progress continues at a pace, with Ausenco Services Pty Ltd leading detailed design work.

The plant’s 3D model has reached 44% completion, with momentum expected to accelerate as more vendor data becomes available.

Procurement is also well advanced, with 12 of the 43 major equipment packages awarded or approved for award, and certified vendor data secured for an additional 11 packages.

The process design, finalised in March 2025, has reached “approved for construction” status, allowing detailed work to proceed with minimal rework risk.

The plant layout, flow diagrams, and mechanical equipment specifications are now well defined, providing a stable foundation for execution.

Utilities, access, and infrastructure

Critical infrastructure is also falling into place. Contracts for water and power supply through NamWater and NamPower are nearing finalisation.

At the same time, associated infrastructure—such as borefields, pipelines, and access roads—has either been completed or is nearing completion.

The site’s initial construction offices and communications systems are already operational, enabling preparations for major works, including bulk earthworks and plant foundation activities scheduled for completion within the current half-year.

Environmental safeguards and water studies

Environmental and hydrogeological studies are reinforcing project sustainability. Monitoring bores, pump testing, and trench sampling have been conducted in the vicinity of sensitive ecological zones near Tumas 3.

Data collected is being used to design safeguards and water management strategies, including a raw water storage facility whose geological base was drilled and mapped in early July.

Financing nearing closure

On the financing side, Deep Yellow is working closely with Nedbank, its Mandated Lead Arranger.

The company has submitted its comprehensive Tumas 2025 DFS to an Independent Technical Expert to support due diligence and secure project funding.

Exploration adds depth

Beyond the main project, Deep Yellow continues exploration on its EPL3496 and EPL3497 licences.

A spectrometer survey identified four surface uranium anomalies on EPL3496, with follow-up work planned.

Meanwhile, drilling has commenced in the “S-Bend” of EPL 3497, with 300 RC holes planned to assess the potential for additional resources.

Next steps

As engineering milestones are ticked off and the site continues to take shape, Deep Yellow is preparing to shift gears.

While the company waits for more supportive uranium prices to justify an investment commitment, it is ensuring that the Tumas Project remains fully prepared to move forward when conditions align—bringing Namibia one step closer to hosting another producing uranium mine..

Share210Tweet131
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Midas kicks off major drill campaign at Otavi Copper Project

Midas finds multiple high-grade copper zones at Deblin near Otavi

October 15, 2026
Serval confirms copper mineralisation in Namibia’s Kaoko Basin

Serval allocates US$7.1m to Namibia copper exploration

October 14, 2026
Japan’s 50% Lofdal stake awaits final approvals

Lofdal’s 50% Japanese ownership deal delayed another 30 days

October 14, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In