• Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
Thursday, January 15, 2026
  • Login
The Extractor Magazine
  • Home
  • News
    • All
    • Africa
    • Biofuels
    • Climate
    • Copper
    • Exploration
    • Lithium
    • Minerals
    • Mining
    • Namibia
    • Nickel
    • Oil & Gas
    • Precious Metals
    • RIGS & VESSELS
    • Silver
    • Uranium
    Eureka Dome – unique rare earths and uranium source

    ReeXploration confirms fully funded 2026 uranium drill programme at Eureka

    Greg Field to start earlier as Deep Yellow managing director ahead of Tumas decisive phase

    Greg Field to start earlier as Deep Yellow managing director ahead of Tumas decisive phase

    Drilling program at Koryx Copper’s Haib mine continues

    Koryx raises C$25 million to accelerate Haib copper studies and exploration

    Midas Minerals to start drilling Otavi Copper Project after acquisition clearance

    Midas uncovers high-grade copper-silver system at Spaatzu in Otavi

    Askari turns to inhouse super technology to identify new targets at Uis lithium project

    Askari targets high-grade tin and tantalum corridor at Uis

    Deep Yellow’s new CEO Greg Field, takes charge at a critical moment for uranium growth

    Deep Yellow refines Tumas strategy as palaeochannel drilling delivers limited upside

    Independent report updates ReconAfrica’s PEL 73 prospective resource estimate

    ReconAfrica adopts shareholder rights plan ahead of 2026 AGM

    Eureka Project expands Namibia’s rare earth frontier

    ReeXploration raises N$18m for Eureka project 2026 drill programme

    Trigon’s smart exit – walks away with about US$25m net gain and a debt-free future

    Trigon hands over Kombat and associated Namibian assets to Horizon

    Midas begins drilling at South Otavi Project

    Midas deploys multiple rigs as Otavi copper exploration gathers pace

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News

Borshoff says deferring Tumas FID minor in scheme of long-term aspirations

by Editor
January 24, 2025
in News
0
Borshoff says deferring Tumas FID minor in scheme of long-term aspirations
516
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Deep Yellow managing director and CEO John Borshoff says the decision to defer the final investment decision on Tumas until March 2025 is minor in the scheme of the long-term aspirations for the project and the company.
The company announced in December 2024 that it was deferring the final investment decision to early March 2025 from Q4 2024.
The deferment results from delays in receiving final costing and quotes for detailed engineering work and the opportunity to undertake further optimisation and enhancements.
Deep Yellow also said the project schedule needed to be refined to arrive at the final investment decision.
Commenting on work completed and progressed during the December quarter, Borshoff said the company has a clear outlook from both the project and uranium market standpoint on ensuring the right platform is established for long-term success.
Borshoff said Tumas is one of the most advanced greenfield uranium development projects available and provides an incredible value-generation opportunity for the company and our stakeholders.
“The delay is minor in the scheme of the project and the company’s long-term aspirations and is in the project’s and our shareholders’ best interest,” Borshoff said.
He said while they continue to progress with early works and expect to be ready to make a final investment decision in March, an improved uranium price will be a primary precondition to starting construction of the processing plant as the current long-term uranium price is not high enough to incentivise greenfield developments.
“We are progressing in debt financing, and with our firm cash reserves, we can make decisions on our terms that are in the best interests of shareholders,” Borshoff said.
The Tumas development has been divided into two clear workstreams: early works and execution phase.
The early works involve non-processing infrastructure, including powerlines, water pipelines, significant roads, site offices, communications, construction camps, and other related facilities managed directly by the Deep Yellow team.
The execution phase is about the processing plant construction and associated works undertaken by the appointed engineering, procurement, and construction management (EPCM) contractor.
Deep Yellow selected Ausenco Services Pty Ltd (Ausenco) as the preferred contractor to deliver detailed engineering services, subject to agreement, for the subsequent EPCM services, with the Tumas execution phase being proactively overseen by the Deep Yellow team to ensure deliverables are achieved according to plan and budget.

Share206Tweet129
Editor

Editor

  • Trending
  • Comments
  • Latest
Ithete says oil and gas could earn Namibia N$7.7b a year

COMMENTARY: Leaders without maps: Namibia’s extractive sector at a crossroads

October 14, 2025
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Japan state-owned company ups interest in Lofdal rare earth project to 40%

Namibia Critical Metals files Lofdal Heavy Rare Earths PFS

January 14, 2026
Andrada’s revenue surged to N$274.5m in quarter ended 31 August from N$243m year earlier

Research outfit says Andrada Mining stands to benefit from rising tin prices

January 14, 2026
Northern Graphite still evaluating funding option for Okanjande project

Okanjande at centre of Northern Graphite’s Saudi battery anode investment

January 14, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In