• Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
Wednesday, September 16, 2026
  • Login
The Extractor Magazine
  • Home
  • News
    • All
    • Africa
    • Biofuels
    • Climate
    • Copper
    • Exploration
    • Lithium
    • Minerals
    • Mining
    • Namibia
    • Nickel
    • Oil & Gas
    • Precious Metals
    • RIGS & VESSELS
    • Silver
    • Uranium
    ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

    ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

    Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

    Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

    Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

    Deep Yellow advances Omahola, S-Bend and Tinkas alongside Tumas

    Deep Yellow spends N$600m on Tumas in 2026 financial year

    Deep Yellow spends N$600m on Tumas in 2026 financial year

    Deep Yellow builds Namibian base as local workforce reaches 45

    Deep Yellow builds Namibian base as local workforce reaches 45

    Unicorn targets Klein Aub copper production within 12 months

    Unicorn targets Klein Aub copper production within 12 months

    Ongwe launches 5,000m maiden drilling at Nguni gold prospect

    Ongwe launches 5,000m maiden drilling at Nguni gold prospect

    Core Energy seeks drilling contractor for maiden Barking Gecko uranium campaign

    Core Energy seeks drilling contractor for maiden Barking Gecko uranium campaign

    71 mining licences inactive, hundreds await decisions

    71 mining licences inactive, hundreds await decisions

    Arkle advances Erongo uranium project towards H1 2027 maiden resource

    Arkle advances Erongo uranium project towards H1 2027 maiden resource

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News

Borshoff says deferring Tumas FID minor in scheme of long-term aspirations

by Editor
January 24, 2025
in News
0
Borshoff says deferring Tumas FID minor in scheme of long-term aspirations
521
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Deep Yellow managing director and CEO John Borshoff says the decision to defer the final investment decision on Tumas until March 2025 is minor in the scheme of the long-term aspirations for the project and the company.
The company announced in December 2024 that it was deferring the final investment decision to early March 2025 from Q4 2024.
The deferment results from delays in receiving final costing and quotes for detailed engineering work and the opportunity to undertake further optimisation and enhancements.
Deep Yellow also said the project schedule needed to be refined to arrive at the final investment decision.
Commenting on work completed and progressed during the December quarter, Borshoff said the company has a clear outlook from both the project and uranium market standpoint on ensuring the right platform is established for long-term success.
Borshoff said Tumas is one of the most advanced greenfield uranium development projects available and provides an incredible value-generation opportunity for the company and our stakeholders.
“The delay is minor in the scheme of the project and the company’s long-term aspirations and is in the project’s and our shareholders’ best interest,” Borshoff said.
He said while they continue to progress with early works and expect to be ready to make a final investment decision in March, an improved uranium price will be a primary precondition to starting construction of the processing plant as the current long-term uranium price is not high enough to incentivise greenfield developments.
“We are progressing in debt financing, and with our firm cash reserves, we can make decisions on our terms that are in the best interests of shareholders,” Borshoff said.
The Tumas development has been divided into two clear workstreams: early works and execution phase.
The early works involve non-processing infrastructure, including powerlines, water pipelines, significant roads, site offices, communications, construction camps, and other related facilities managed directly by the Deep Yellow team.
The execution phase is about the processing plant construction and associated works undertaken by the appointed engineering, procurement, and construction management (EPCM) contractor.
Deep Yellow selected Ausenco Services Pty Ltd (Ausenco) as the preferred contractor to deliver detailed engineering services, subject to agreement, for the subsequent EPCM services, with the Tumas execution phase being proactively overseen by the Deep Yellow team to ensure deliverables are achieved according to plan and budget.

Share208Tweet130
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

ReconAfrica seeks clearance to transport hazardous chemicals for KW1X testing

September 16, 2026
Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

Deep Yellow yet to decide Tumas debt size before Nedbank goes to market

September 16, 2026
Deep Yellow to mobilise Tumas contractors in August as project advances towards anticipated FID

Deep Yellow advances Omahola, S-Bend and Tinkas alongside Tumas

September 16, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In