    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

    Pancontinental opens PEL 87 virtual data room to bidders

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Chamber of Mines to engage Govt after Namibia shed 3 points in Fraser Institute mining survey

    Namibia can unlock 18 000 mining jobs and billions if policy bottlenecks are cleared – Malango

    Uis Tin Mine: The world’s largest undeveloped open-cast hard rock tin deposit

    Andrada delays £7.7m loan repayment to fund Uis mine expansion

    Connected Minerals completes maiden RC drilling at Etango North-East, moves rig to Swakopmund Uranium Project

    Connected pauses work on its Namibian uranium assets as cash falls to A$2.8m

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas declares maiden 10.5Mt at 1.6% copper and 21g/t silver resource at Otavi projects

    Public review opens for Koppies West uranium project application

    Elevate grows Namibian uranium footprint to 116 million pounds

    Galp’s long game: From HRT’s early dry wells to Namibia’s new oil dawn

    Galp confirms three-well drilling and testing campaign for Mopane

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News

Borshoff says deferring Tumas FID minor in scheme of long-term aspirations

by Editor
January 24, 2025
in News
0
Borshoff says deferring Tumas FID minor in scheme of long-term aspirations
517
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter

Deep Yellow managing director and CEO John Borshoff says the decision to defer the final investment decision on Tumas until March 2025 is minor in the scheme of the long-term aspirations for the project and the company.
The company announced in December 2024 that it was deferring the final investment decision to early March 2025 from Q4 2024.
The deferment results from delays in receiving final costing and quotes for detailed engineering work and the opportunity to undertake further optimisation and enhancements.
Deep Yellow also said the project schedule needed to be refined to arrive at the final investment decision.
Commenting on work completed and progressed during the December quarter, Borshoff said the company has a clear outlook from both the project and uranium market standpoint on ensuring the right platform is established for long-term success.
Borshoff said Tumas is one of the most advanced greenfield uranium development projects available and provides an incredible value-generation opportunity for the company and our stakeholders.
“The delay is minor in the scheme of the project and the company’s long-term aspirations and is in the project’s and our shareholders’ best interest,” Borshoff said.
He said while they continue to progress with early works and expect to be ready to make a final investment decision in March, an improved uranium price will be a primary precondition to starting construction of the processing plant as the current long-term uranium price is not high enough to incentivise greenfield developments.
“We are progressing in debt financing, and with our firm cash reserves, we can make decisions on our terms that are in the best interests of shareholders,” Borshoff said.
The Tumas development has been divided into two clear workstreams: early works and execution phase.
The early works involve non-processing infrastructure, including powerlines, water pipelines, significant roads, site offices, communications, construction camps, and other related facilities managed directly by the Deep Yellow team.
The execution phase is about the processing plant construction and associated works undertaken by the appointed engineering, procurement, and construction management (EPCM) contractor.
Deep Yellow selected Ausenco Services Pty Ltd (Ausenco) as the preferred contractor to deliver detailed engineering services, subject to agreement, for the subsequent EPCM services, with the Tumas execution phase being proactively overseen by the Deep Yellow team to ensure deliverables are achieved according to plan and budget.

Share207Tweet129
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

April 30, 2026
Northern Graphite plans restarting Okanjande in 2027

Okanjande moves closer to restart after Northern clears US$22m debt burden

April 30, 2026
Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

Pancontinental opens PEL 87 virtual data room to bidders

April 30, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In