    Mining exports hit N$64.7bn as Namibia shifts focus to energy, oil and gas — Nandi-Ndaitwah

    Namibia says 51% free-carry mine ownership not policy

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas hits 50m at 7.9% CuEq in highest-grade Otavi intercept yet

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

    Namibia’s PEL 87 comes of age as one of most technically advanced pre-drill plays

    Pancontinental opens PEL 87 virtual data room to bidders

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Mining pays Namibia N$7.8 billion as corporate tax jumps 55%

    Chamber of Mines to engage Govt after Namibia shed 3 points in Fraser Institute mining survey

    Namibia can unlock 18 000 mining jobs and billions if policy bottlenecks are cleared – Malango

    Uis Tin Mine: The world’s largest undeveloped open-cast hard rock tin deposit

    Andrada delays £7.7m loan repayment to fund Uis mine expansion

    Connected Minerals completes maiden RC drilling at Etango North-East, moves rig to Swakopmund Uranium Project

    Connected pauses work on its Namibian uranium assets as cash falls to A$2.8m

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

    Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

    Midas declares maiden 10.5Mt at 1.6% copper and 21g/t silver resource at Otavi projects

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home Magazine

Kokoseb Gold Project to create up to 1,500 jobs

by Editor
November 23, 2025
in Magazine
0
Kokoseb Gold Project to create up to 1,500 jobs
507
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

The Kokoseb Gold Project is set to become one of Namibia’s largest rural employers, with early projections showing an enormous labour footprint long before the first gold bar is poured.

At the height of construction, the project will need between 1,100 and 1,500 workers, drawing people from Uis, Okombahe and surrounding communities into what will be one of the most significant job-creation drives in the Erongo Region in years.

Once Kokoseb moves into steady-state operations, the workforce will stabilise at 800 to 900 permanent jobs, spread across the mine’s processing plant, mining operations, workshops, laboratories, planning offices and environmental departments.

About 120 employees will keep the processing plant running; 200 people will fill technical roles, administration, safety, health, environment and management; around 100 employees will handle maintenance; and the mining component will absorb roughly 450 positions, from drill-and-blast teams to load-and-haul operators, pit controllers and supervisors.

This workforce will sit within a contractor-driven mining model, with a preferred mining contractor expected to employ 800 to 900 people at peak production.

Within that group will be a management team, a mine technical services division, a support services arm, drill-and-blast specialists, load-and-haul crews and a fully staffed maintenance team working around the clock to keep the mobile fleet moving.

These numbers make Kokoseb not just another gold project but a significant employment centre taking shape on Exclusive Prospecting Licence (EPL) 4818 between Uis and Okombahe—about 15 kilometres from Okombahe and 30 kilometres from Uis.

The scale mirrors that of Namibia’s two established gold mines, B2Gold’s Otjikoto and QKR’s Navachab, and the project’s operational design follows similar patterns. Mining will use conventional open-pit methods: drilling and blasting rock in 5-metre ore benches and 10-metre waste benches, loading material with medium-sized hydraulic excavators, and hauling it to waste dumps or the Run-of-Mine pad for crushing and gold extraction.

Processing will take place on-site, through cyanide leaching, carbon-in-pulp extraction, electrowinning and smelting in an induction furnace to produce gold bars.

It is a high-impact, highly mechanised operation that will run 361 days a year, 24 hours a day, using three rotating eight-hour shifts.

With approximately 80 per cent of equipment operators expected to enter at the unskilled level, the mine’s localisation plan will focus on training and upskilling, and on gradually transitioning responsibilities to Namibian workers.

The story behind this massive employment engine began with one of the fastest large-scale gold discoveries in recent African mining history. WIA Gold announced its maiden Inferred Mineral Resource Estimate for Kokoseb in May 2023—1.3 million ounces at 1.0 g/t, including a high-grade core of 0.72 million ounces at 1.5 g/t.

These figures arrived barely twelve months after drilling began. By April 2024, the resource had grown by 63 per cent to 2.1 million ounces at 1.0 g/t, with a higher-grade zone of 1.53 million ounces at 1.4 g/t.

Early metallurgical results have been equally encouraging, with gold recoveries exceeding 91 per cent through gravity and direct leach processes.

This rapid growth has positioned Kokoseb as one of the lowest-cost modern gold discoveries globally, with discovery costs of under US$3 per ounce. Encouragingly, the deposit remains open in all directions and at depth, leaving room for further expansion as drilling continues.

The mining method planned for Kokoseb reflects both efficiency and precision. Ore and selective waste will be mined in 5-metre benches, while broad waste zones will be mined in 10-metre benches, split into 5-metre flitches for better control.

Excavators will range from 130-tonne hydraulic backhoes for selective loading to 200-tonne units for bulk material movement. Haulage will rely on 100-tonne off-highway rigid trucks, supported by a suite of secondary and ancillary equipment.

Standard open-pit drill rigs capable of drilling holes up to 171 mm in diameter will handle blast preparation.

A globally experienced start-up team will lead the early development years, ensuring safe commissioning and a disciplined ramp-up.

Over time, the skills and technical functions will transfer to trained Namibian teams, supported by the project’s localisation plan.

Ownership of Kokoseb lies with Mandarin Investments (Pty) Ltd, a joint venture between Damaran Exploration Namibia (Pty) Ltd and Epangelo Mining Company (Pty) Ltd. Damaran Exploration is a subsidiary of WIA Gold, the operator and parent company driving the project’s vision and development path.

As Kokoseb advances toward a final investment decision, the employment figures, the expanding mineral resource and the robust mine design all point toward a transformative operation.

Kokoseb has the potential to reset local economies, build new skills, and deliver long-term opportunities that extend far beyond the open pit.

Share203Tweet127
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
Mining exports hit N$64.7bn as Namibia shifts focus to energy, oil and gas — Nandi-Ndaitwah

Namibia says 51% free-carry mine ownership not policy

May 4, 2026
Midas defines 211kt copper equivalent resource at Otavi, outlines open-pit potential

Midas hits 50m at 7.9% CuEq in highest-grade Otavi intercept yet

May 4, 2026
Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

Sintana says Namibia drives growth as Mopane rises to 1.38bn boe

April 30, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In