Huaye Botswana Mining has begun recruiting 40 workers for underground operations at the Khoemacau Copper Mine in Botswana, ahead of the commencement of a five-year mining services programme in January 2027.
The recruitment drive, advertised in Botswana’s DailyNews on 20 November 2026, follows a contract signed with Khoemacau Copper Mining on 21 May 2026 for underground mining services at the Zone 5 and Zeta mines.
The agreement covers 67 months, including a seven-month mobilisation period ending in December 2026 and 60 months of underground mining services beginning on 1 January 2027.
Under the agreement, Khoemacau will provide Huaye with a US$20 million advance payment, which will be recovered over 12 months.
MMG, the Hong Kong-listed owner of Khoemacau, has established a transaction ceiling of US$35 million for 2026 and US$200 million annually between 2027 and 2031 under the Huaye agreement.
The annual limits provide for a cumulative maximum of US$1.035 billion over the contract period, although they do not represent guaranteed payments or the fixed value of the agreement.
Huaye’s recruitment advertisement covers 40 positions across underground mining, electrical and mechanical maintenance, concrete production and mine surveying.
The company is seeking six jumbo operators, three underground loader operators, five shotcrete supervisors and three shotcrete operators.
Other positions include electrical foremen, electricians, auto electricians, mechanical foremen, maintenance fitters and mine surveyors.
The vacancies are based at the Zone 5N and Zeta operations near Toteng, with employees expected to work on rotational or site-based schedules.
Huaye said suitably qualified Botswana citizens would receive first preference in accordance with applicable legislation and company policies.
Applications will remain open until the positions are filled.
The recruitment programme forms part of preparations for Khoemacau’s expansion, which MMG has approved at an estimated investment of approximately P13 billion.
The expansion is intended to increase annual copper production to approximately 130,000 tonnes of copper in concentrate by the second quarter of 2028 and extend the mine’s operating life beyond 20 years.
MMG disclosed the Huaye agreement to the Hong Kong Stock Exchange on 21 May 2026, alongside a separate underground mining contract awarded to MCC23 Botswana for the Mango mine.
Both contractors are associated with China Minmetals Corporation, MMG’s ultimate controlling shareholder.
The agreements were consequently classified as continuing connected transactions under Hong Kong Stock Exchange listing rules.
MMG said the contractors were selected through a tender process that considered pricing, technical capability, operational feasibility, safety, previous performance and localisation plans.
The company disclosed that seven potential service providers had been invited to tender during 2025, including independent contractors and companies connected to MMG.
Under the Huaye agreement, charges cover mobilisation, equipment, underground mining services and other contractual requirements.
Huaye will submit monthly invoices, which must be certified by Khoemacau before payment within seven days of receipt of a valid tax invoice.
MMG said the longer contract duration would allow contractors to invest in training, maintenance facilities and infrastructure while avoiding repeated tendering during the development period.
Huaye’s appointment forms part of a wider contractor arrangement at Khoemacau.
In 2025, MMG awarded Chinese mining contractor JCHX a separate five-year underground mining contract for Zone 5, which JCHX valued at approximately US$805 million.
The JCHX contract commenced in July 2025, following the departure of Australian mining contractor Barminco.
Huaye’s 2026 contract covers Zone 5 and Zeta expansion activities, while MCC23 Botswana is responsible for underground mining services at Mango.
MMG has also placed equipment orders to support the expansion, including a September 2026 order valued at approximately US$64 million with Swedish mining equipment manufacturer Epiroc.
The equipment includes underground drilling rigs, loaders and mine trucks, with deliveries scheduled to begin during the final quarter of 2026.
The latest recruitment programme indicates that Huaye is preparing its workforce for the next phase of Khoemacau’s underground development as the mine moves towards its expanded production capacity.