    NDP6 – Five mines to power a nuclear future by 2030

    Bannerman reserves 40% of Etango uranium for buyers outside Chinese partnership

    Bannerman eyes US$367m expansion to double Etango uranium processing capacity

    Bannerman eyes US$367m expansion to double Etango uranium processing capacity

    Bannerman identifies three uranium exploration prospects around Etango

    Bannerman identifies three uranium exploration prospects around Etango

    Core Energy starts 2 650m uranium drilling at Barking Gecko in Namibia

    Core Energy starts 2 650m uranium drilling at Barking Gecko in Namibia

    Aldoro completes Avondschaduw drilling, moves rig to Kameelburg for three niobium holes

    Aldoro completes Avondschaduw drilling, moves rig to Kameelburg for three niobium holes

    Okopa pursues early copper production at Cornerstone Copper Project

    Okopa pursues early copper production at Cornerstone Copper Project

    QatarEnergy acquires 25% stake in Chevron’s PEL 82

    QatarEnergy grows offshore licence count to five

    Forsys’ Norasa in the making

    Asarian begins 4,500-metre uranium drilling programme at Namibplaas

    Cobre plans copper demonstration plant at Botswana’s Ngami Project in second half of 2027

    Cobre plans copper demonstration plant at Botswana’s Ngami Project in second half of 2027

    Leviathan intersects 0.47% copper at Central Project in Botswana

    Leviathan intersects 0.47% copper at Central Project in Botswana

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Bannerman eyes US$367m expansion to double Etango uranium processing capacity

by Editor
November 12, 2026
in Uranium
0
Bannerman eyes US$367m expansion to double Etango uranium processing capacity
498
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

Bannerman Energy is considering a US$367 million expansion of its Etango uranium project in Namibia that could double annual processing capacity from eight million to 16 million tonnes and increase uranium production to 6.7 million pounds a year.

The proposed expansion, outlined in the company’s investor presentation released on 11 November 2026, would follow the development of the initial Etango-8 operation, which is now under full-scale construction following a positive final investment decision in October.

Bannerman expects the first phase to produce an average of 3.5 million pounds of uranium oxide annually over an initial 15-year mine life, with first production scheduled for 2028.

The larger Etango-16 operation could increase annual output to 6.7 million pounds after expansion, while extending total production to 95.2 million pounds over a 16-year operating period.

The US$367 million represents forecast additional capital expenditure for the expansion, separate from the US$353 million required to develop the initial Etango-8 operation.

Bannerman has not announced a final investment decision on the expansion, which remains a longer-term development option.

Production could nearly double

The proposed expansion would increase annual ore-processing capacity from eight million to 16 million tonnes, allowing Bannerman to extract more uranium from the existing resource base.

According to the company’s technical projections, the expanded operation could produce 95.2 million pounds of uranium oxide over its operating life, compared with 52.6 million pounds under the initial development plan.

At an assumed uranium price of US$95 per pound, the expanded project is forecast to generate US$2.91 billion in post-tax net cash flow over its operating life.

These projections are based on earlier technical studies and remain subject to future investment decisions, market conditions and development requirements.

Bannerman said the expansion could be pursued after the initial mine has entered production and completed its ramp-up.

The company is also examining opportunities to extend mining operations through further exploration at Etango and surrounding prospects, including Hyena, Onjamba and Ompo.

Initial mine fully funded

The expansion plans come as Bannerman moves ahead with construction of the initial Etango operation, approximately 30 kilometres south-east of Swakopmund.

The company confirmed that its remaining pre-production capital requirements are fully funded through existing joint venture cash following the completion of its strategic investment agreement with CNNC Overseas Limited.

The Chinese company invested US$320.4 million in the transaction, including US$294.5 million paid into the Etango joint venture and US$25.9 million reimbursed to Bannerman.

CNNC Overseas holds 45% of the joint venture, while Bannerman retains 55%.

The joint venture owns 95% of the Etango project, with Namibia’s One Economy Foundation holding the remaining 5%.

Bannerman reported that the joint venture had approximately US$295 million in cash at 30 September 2026, while the Australian company separately held approximately A$175 million.

The company said these funds were sufficient to complete construction, ramp-up and the transition to commercial uranium production without additional project debt.

Construction moves towards completion of early works

Bannerman reported that bulk earthworks at Etango were approximately 99% complete, while the first phase of the permanent water supply pipeline had reached about 90%.

Approximately 14,700 cubic metres of concrete had been poured, representing 86% of the requirements for the first two construction phases.

The project had approximately 523 contractor personnel on site, with Namibian companies undertaking major construction activities.

Bannerman is also progressing the design of a 132-kilovolt electricity transmission line and substations under its power supply arrangements with NamPower.

The proposed expansion would build on this initial infrastructure investment, although additional plant capacity and supporting facilities would be required.

The company has not specified when it would make an investment decision on Etango-16.

Its immediate priority remains completing the US$353 million initial development and bringing Etango into production in 2028.

Share199Tweet125
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Namibia’s next multi-mineral growth province

Celsius Resources targets June deal for Opuwo Cobalt-Copper project sale

May 25, 2026
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
NDP6 – Five mines to power a nuclear future by 2030

Bannerman reserves 40% of Etango uranium for buyers outside Chinese partnership

November 12, 2026
Bannerman eyes US$367m expansion to double Etango uranium processing capacity

Bannerman eyes US$367m expansion to double Etango uranium processing capacity

November 12, 2026
Bannerman identifies three uranium exploration prospects around Etango

Bannerman identifies three uranium exploration prospects around Etango

November 12, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Subscribe now to receive all mining sector and related news!

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Extractor Magazine will use the information you provide on this form to be in touch with you and to provide updates and marketing.
Subscribe