    African Pioneer begins 7,000m drilling at Ongombo and Ongeama copper projects

    African Pioneer begins 7,000m drilling at Ongombo and Ongeama copper projects

    Deep Yellow locks in water, local ownership ahead of Tumas investment decision

    Deep Yellow postpones Tumas investment decision beyond 2026

    Midas kicks off major drill campaign at Otavi Copper Project

    Midas finds multiple high-grade copper zones at Deblin near Otavi

    Serval confirms copper mineralisation in Namibia’s Kaoko Basin

    Serval allocates US$7.1m to Namibia copper exploration

    Madison Metals starts drilling at Khan Project in Namibia

    Critical One plans Critical Two Energy for Namibian uranium assets after failed US$3.5m sale

    Skeleton Coast Uranium closes N$95m funding, completes Namibia licence deal

    Skeleton Coast commits N$13.75m to uranium exploration near Langer Heinrich

    Higher uranium prices cushion 19% production drop at Langer Heinrich

    Higher uranium prices cushion 19% production drop at Langer Heinrich

    Arkle brings forward second uranium target after encouraging Namibia drilling

    Arkle finds uranium along 2.9km stretch near Trekkopje

    Keras becomes Okopa after securing 51% stake in Cornerstone Mining

    Keras becomes Okopa after securing 51% stake in Cornerstone Mining

    Noronex sees Powerline drill campaign as key toward commercial-scale discovery

    Noronex exits DorWit, its first Namibian copper projects

    Trending Tags

  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item
No Result
View All Result
The Extractor Magazine
No Result
View All Result
Home News Uranium

Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion

by Editor
April 29, 2026
in Uranium
0
Bannerman targets Etango FID after mid-2026 Chinese-backed deal completion
558
SHARES
1.6k
VIEWS
Share on FacebookShare on Twitter

Bannerman Energy managing director and chief executive officer Gavin Chamberlain says the company expects a final investment decision on its Etango Uranium Project later this year after securing a Chinese-backed funding solution that provides a debt-free path to construction and a cornerstone buyer for 60% of future production.

The CNNC Overseas Limited transaction is targeted for completion in mid-2026, subject to remaining regulatory and contractual conditions, with Bannerman guiding that a positive final investment decision is expected shortly thereafter and during the second half of 2026.

The agreement will see CNNC Overseas invest up to US$321.5 million for a 45% interest in Bannerman Energy (UK) Ltd, the holding company that owns 95% of the Etango project in Namibia.

“A transformational milestone during the quarter was the announced project funding solution through a strategic partnership with CNNC Overseas Limited.

This transaction provides a clear, debt free pathway to development and an expected Final Investment Decision later this year. Put simply, it is the final piece that unlocks the development and operation of the Etango Project,” Chamberlain said.

Bannerman will retain a 55% stake in the joint venture, equating to an underlying 52.25% economic interest in Etango, while Namibia’s One Economy Foundation will continue to hold a 5% loan-carried shareholding.

Despite the incoming strategic investor, Bannerman will remain in control of the venture through majority ownership and the right to appoint three of five board directors, as well as three of five key executive management positions including chief executive officer at operating company level.

The company said the structure removes the need for anticipated commercial debt during construction and ramp-up, materially reducing project risk while preserving corporate flexibility.

Each shareholder will fund future capital expenditure and operating costs pro rata to their 55% and 45% interests.

Under the offtake arrangement, CNNC Overseas will have life-of-mine rights to purchase 60% of actual uranium production from Etango under market-based pricing linked to a combination of spot and long-term uranium price indices. Bannerman will independently market the remaining 40% of output.

Completion of the transaction remains subject to several conditions, including clearance from the Namibian Competition Commission, Chinese regulatory filings, amendments to the One Economy Foundation funding agreement and execution of key Etango infrastructure supply contracts.

Bannerman said all conditions must be met or waived by 30 September 2026 unless extended by mutual agreement.

At site level, Bannerman said approximately A$53.61 million had already been spent on Etango early works by 31 March, with a further A$31.4 million committed.

All major workstreams remain aligned with the targeted second-half 2026 investment decision.

The contractor workforce has risen to more than 560 personnel across four Namibian contractors — Namibbeton, K Neumayer Civil Contractors, Tulela Mining and Construction and AN Construction — while the project has achieved 500,000 lost-time-injury-free hours.

Bulk earthworks were 66.5% complete at quarter-end, with the main focus on heap leach pad construction and wet plant terraces. Production of drainage aggregate for the heap leach facility had reached approximately 24% of total requirements.

Bannerman also reported that 5,509 cubic metres of concrete had been poured across the primary crusher, stockpile tunnel and fine ore silo packages, representing roughly 32% completion for those contracts.

Long-term utilities infrastructure is also progressing. Phase 1 of the permanent water supply pipeline was about 70% complete and ahead of schedule, while Bannerman confirmed it had signed a definitive power supply agreement with NamPower.

The lease agreement for the acid storage and handling facility at Namport in Walvis Bay has also been signed.

Bannerman ended March with A$69.9 million in cash and A$12.7 million in liquid assets. It also holds approximately 101.3 million shares in Namibia Critical Metals Inc., valued at around A$30.1 million at quarter-end.

The company said the long-term uranium price rose US$6 during the quarter to US$93/lb by 31 March, while spot prices moved between US$82/lb and US$101.50/lb before closing at US$84.50/lb.

Etango is located in Namibia’s Erongo Region, one of the world’s premier uranium districts and home to producing operations including Rössing Uranium, Husab Mine and Langer Heinrich Mine.

Bannerman’s definitive feasibility study outlined average annual production of 3.5 million pounds U3O8 under the Etango-8 development case, with later studies indicating potential expansion to 6.7 million pounds annually.

Share223Tweet140
Editor

Editor

  • Trending
  • Comments
  • Latest
Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

Private company led by John Sisay to revive Tschudi, Otjihase, Matchless and Berg Aukas mines  

February 6, 2024
ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

ReconAfrica to drill first well in the Damara Fold Belt after raising N$238m

April 3, 2024
Gratomic targets 12,000t of vein graphite from Aukam mine this year

Gratomic targets 12,000t of vein graphite from Aukam mine this year

February 3, 2024
Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

Askari Metals puts hopes on Kestrel Pegmatite within the Uis Lithium Project

3
Namibia holds 26 million ounces of silver

Namibia holds 26 million ounces of silver

3
2024 HOPEFULS: Langer Heinrich’s return after five years

2024 HOPEFULS: Langer Heinrich’s return after five years

2
African Pioneer begins 7,000m drilling at Ongombo and Ongeama copper projects

African Pioneer begins 7,000m drilling at Ongombo and Ongeama copper projects

October 16, 2026
Deep Yellow locks in water, local ownership ahead of Tumas investment decision

Deep Yellow postpones Tumas investment decision beyond 2026

October 16, 2026
Midas kicks off major drill campaign at Otavi Copper Project

Midas finds multiple high-grade copper zones at Deblin near Otavi

October 15, 2026
  • Home
  • News
  • Magazine
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

No Result
View All Result
  • Home
  • News
  • Magazine
    • Current Edition
    • Previous Editions
  • Climate
  • Minerals
  • Mining
  • All About Namibia’s Extractive Sector
  • Contact
  • Menu Item

Copyright © 2023 The Extractor Magazine. | Powered by: Impeccable Tech & Designs

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In